ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 YU YUM SS97601D SW AVE E EXTENSION; CO. 23RD - CO. 1 ZW1L CONSTRUCT NEW ROADWAY OLIVIER MIRZA
602-712-4032
TBD Lee Makler
602-712-8579
Current Program Budget $1,410,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2024-06-19 A
Stage 3 - 60% 2024-10-25 A
Stage 4 - 95% 2025-03-08
EPG Clearance 2025-01-18
RW Clearance 2025-08-09
URR Clearance 2026-03-07
Stage 5 - 100% 2026-03-07
Advertise 2026-04-25
Bids Opening 2026-06-20




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation