PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 1/31/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/2/2023 1:12:34 PM | Thomas Oreilly | (602) 712-2587 | 205 S 17th Ave, 293, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TWO GUNS - DENNISON | PAVEMENT REHABILITATION | ZS1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | I-40 | Coconino | 230 | F057901D | 9.3 | 040-D(247)T |
16. Original Program Budget: $450,000 | 17. Original Program Item #: 103132 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$450,000 | ($35,000) (0%) | $415,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 450 Item #:103132 (100pct State) FY:0 FundSRC: Desc: | $ -35 Item #:70023 (100pct State) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This request is to establish design for a pavement rehabilitation project. Staff = $316K Consultant = $60K ICAP = $39K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |