PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/15/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/18/2025 10:11:07 AM Thomas Oreilly (602) 712-2587 205 S 17th Ave, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
TWO GUNS - DENNISON PAVEMENT REHABILITATION ZS1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 229 F057901D 10.28 040-D(247)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $475,000 17. Original Program Item #: 103132
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$475,000 $25,000 (0%) $500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 450 Item #:103132 (100pct State) FY:0 FundSRC: Desc: $ 25 Item #:72725 (100 pct. State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
This request is to add budget for the project design. Following Stage IV the pavement sections changed to address travel lane deterioration. The depth and pavement material types changed twice. Staff = $23K ICAP = $2K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 3/11/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2025 8:42:35 AM Thomas Oreilly (602) 712-2587 205 S 17th Ave, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
TWO GUNS - DENNISON PAVEMENT REHABILITATION ZS1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 229 F057901C 10.28 040-D(247)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $49,162,000 17. Original Program Item #: 103132
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$49,162,000 $0 (0%) $49,162,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 49162 Item #:103132 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 2025 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 3/21/2025 23a. Bid Adv Date: 4/18/2025

25. DESCRIPTION OF REQUEST
Defer project to 4th Quarter.
26. JUSTIFICATION
Due to District request to provide sections of deep pavement repair, the advertisement date will move from the 3rd quarter to the 4th quarter.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Schedule. Item(s) Approved.


PRB Meeting Date: 12/10/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/12/2024 9:28:44 AM Thomas Oreilly (602) 712-2587 205 S 17th Ave, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
TWO GUNS - DENNISON PAVEMENT REHABILITATION ZS1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 229 F057901D 10.28 040-D(247)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $415,000 17. Original Program Item #: 103132
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$415,000 $60,000 (0%) $475,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 450 Item #:103132 (100pct State) FY:0 FundSRC: Desc: $ 60 Item #:72725 (100 pct. State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
This request is to add budget for project design. At Stage III review a mainline profile issue was found at the Meteor City TI approaches and departures which is causing ponding at the bridge deck joints, resulting in joint damage and erosion issues. In order to correct this, survey was needed as well as updates to the MDR, design, and plans. Staff = $55K ICAP = $5K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 1/31/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/2/2023 1:12:34 PM Thomas Oreilly (602) 712-2587 205 S 17th Ave, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
TWO GUNS - DENNISON PAVEMENT REHABILITATION ZS1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40 Coconino 230 F057901D 9.3 040-D(247)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $450,000 17. Original Program Item #: 103132
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$450,000 ($35,000) (0%) $415,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 450 Item #:103132 (100pct State) FY:0 FundSRC: Desc: $ -35 Item #:70023 (100pct State) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This request is to establish design for a pavement rehabilitation project. Staff = $316K Consultant = $60K ICAP = $39K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation