PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/18/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/1/2023 2:37:03 PM Velvet Mathew (602) 712-3062 1611 W Jackson St, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 H800601D 0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $200,000 17. Original Program Item #: 44811
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$200,000 $0 (0%) $200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 200 Item #: 44811 (WARNER STREET BRIDGE - construct new bridge) FY:0 FundSRC: Desc: $ -200 Item #:49923 (RARF) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change schedule
26. JUSTIFICATION
MAG is deferring the Design of this project from FY23 to FY25 due to change in priorities. Subject to MAG approval, anticipated in May, 2023
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Request Withdrawn.


PRB Meeting Date: 5/19/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/2/2020 9:26:10 AM Myrna Bondoc (602) 712-7622 206 S 17th Ave, , 310B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER STREET BRIDGE DESIGN NEW BRIDGE ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 H800601D 0.0 RARF085-B(204)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $200,000 17. Original Program Item #: 44811
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$200,000 ($200,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 17-0006733
$ 200 Item #: 44811 (RARF) FY:0 FundSRC: Desc: $ -200 Item #:49920 (RARF ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 20 21a. Fiscal Year: 21  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Design project to FY21.
26. JUSTIFICATION
MAG requested to defer the Design project from FY20 to FY21 due to change in project priorities. Contingent on approval by MAG Regional Council on June 24, 2020.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Delete Project. Item(s) Approved. Subject to PPAC Approval. Contingent on approval by MAG Regional Council on June 24, 2020.


PRB Meeting Date: 5/19/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/2/2020 9:26:19 AM Myrna Bondoc (602) 712-7622 206 S 17th Ave, , 310B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 H800601C 0.0 RARF085-B(204)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $5,300,000 17. Original Program Item #: 44811
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$5,300,000 ($5,300,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 17-0006733
$ 5300 Item #: 44811 (RARF) FY:0 FundSRC: Desc: $ -5300 Item #:49920 (RARF ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 20 21a. Fiscal Year: 21  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Construction project to FY21.
26. JUSTIFICATION
MAG requested to defer the Construction project from FY20 to FY21 due to change in project priorities. Contingent on approval by MAG Regional Council on June 24, 2020.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Delete Project. Item(s) Approved. Subject to PPAC Approval. Contingent on approval by MAG Regional Council on June 24, 2020.


PRB Meeting Date: 4/2/2019
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/2/2019 12:59:19 PM Myrna Bondoc (602) 712-7622 206 S 17th Ave, , 310B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 H800601C 0.0 RARF085-B(204)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $5,300,000 17. Original Program Item #: 44811
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$5,300,000 ($5,300,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 5300 Item #:44811 (RARF) FY:2020 FundSRC:. Desc:WARNER STREET BRIDGE $ -5300 Item #:44811. (RARF ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 19 21a. Fiscal Year: 20  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer construction from FY19 to FY20.
26. JUSTIFICATION
Due to MAG Freeway Life Cycle Program rebalancing, project priorities are currently unknown therefore we request to defer construction from FY19 to FY20 until MAG has completed their rebalancing effort. This action has been approved by MAG Regional Council on August 31, 2018.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/19/2016
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/27/2016 9:41:33 AM Eric Prosnier (602) 712-8495 1611 W Jackson St, , EM01
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Warner Street Bridge Design New Bridge ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 H800601D 085-B(204)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 3352
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $430,000 (0%) $430,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 430 Item #:42416 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a design project
26. JUSTIFICATION
Design (under TRACS H5955) put on hold in 2008 at 95-percent design. City of Buckeye and new developer are committed to completing project. ADOT committed to completing design of bridge (Construction programmed for FY18, Item# 44811). MAG TIP # DOT 16-413 Consultant = $330K Staff = $60K ICAP = $40K Total = $430K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 3/15/2011
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/1/2011 12:49:30 PM Velvet Mathew (602) 712-3062 1611 W Jackson St, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 H800601C 0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $5,300,000 17. Original Program Item #: 44811
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$5,300,000 $0 (0%) $5,300,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 08-148-I with the Town of buckeye
$ 5300 Item #:44811 (.) FY:2020 FundSRC:. Desc:WARNER STREET BRIDGE  

Current Approved New Project/Change Request  
21. Fiscal Year: 11 21a. Fiscal Year: 13  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer from FY11 to FY13.
26. JUSTIFICATION
The Town of Buckeye has no plans to construct Warner Street at this time. JPA was executed on March 18, 2009. In the JPA, the construction of the Warner Street Bridge is a future project to be constructed by the State (Recital II-2h).
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/14/2009
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/22/2009 9:53:35 AM Velvet Mathew (602) 712-3062 1611 W Jackson St, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Warner Street Bridge Construct a new bridge ZN1J
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 85 Maricopa 153.2 _  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $11,000,000 (0%) $11,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 11000 Item #:OTHR9 (RTP CASH FLOW) FY:2009 FundSRC:. Desc:OTHER SOURCE  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 11  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Create a new bridge construction project.
26. JUSTIFICATION
Anticipate construction of the project with the SR 85, Hazen Rd to Broadway Rd (H7602).
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation