PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 10/1/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/3/2024 9:03:49 AM Ted Smithwick (602) 228-5378 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
13 YUMA COUNTYWIDE LOCATIONS INSTALL PAVEMENT MARKINGS YO1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 0000 Yuma YYU T037601C 98.0 HSIPYYU-0(220)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $1,701,000 17. Original Program Item #: 101666
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$1,701,000 $0 (0%) $1,701,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 1700 Item #:101666 (HSIP 100) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 2/27/2025 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change project name.
26. JUSTIFICATION
This project will upgrade existing pavement markings on 13 various roadway segments within Yuma County. Requesting to change the project name to match the PE authorization form. Request the project name be changed to: "YUMA COUNTY ROADWAY SEGMENTS".
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Item(s) Approved.


PRB Meeting Date: 12/13/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/4/2023 2:42:17 PM Lana Nabaty (602) 712-2217 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
13 YUMA COUNTY ROADWAY SEGMENTS INSTALL PAVEMENT MARKINGS YO1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 0000 Yuma YYU T037601D 98.0 HSIP YYU-0(220)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $30,000 17. Original Program Item #: 101666
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$30,000 $0 (0%) $30,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008652-I
$ 30 Item #:101666 (100pct HSIP ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project will upgrade pavement marking width from 4� to 6� on 13 roadways in Yuma County. Total project length is approximately 98 miles. Construction is planned for FY25. Staff-$30k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 12/13/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/7/2023 1:23:26 PM Lana Nabaty (602) 712-2217 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
13 YUMA COUNTYWIDE LOCATIONS INSTALL PAVEMENT MARKINGS YO1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 0000 Yuma YYU T037603D 98.0 HSIP YYU-0(220)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $107,000 17. Original Program Item #: 101666
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$107,000 $0 (0%) $107,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008652-I
$ 107 Item #:101666 ($106,500.00. 100pct HSIP) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project will upgrade pavement marking width from 4� to 6� on 13 roadways in Yuma County. Total project length is approximately 98 miles. Construction is planned for FY25. Consultant-$107k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation