PRB Meeting Date: 3/11/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2025 8:39:19 AM Chris Rodriguez (602) 712-4642 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MARYLAND AVE - BETHANY HOME RD & 43RD AVE - 59TH A IMPROVE SIDEWALKS & ADA RAMPS YI1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa GLN T037301C 0.0 CMAQGLN-0(269)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $5,229,000 17. Original Program Item #: 103069
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$5,229,000 $0 (0%) $5,229,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008646-I
$ 3428 Item #:103069 (CMAQ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 5/27/2025 23a. Bid Adv Date: 5/27/2026

25. DESCRIPTION OF REQUEST
Defer project form FY25 to FY26 for construction
26. JUSTIFICATION
Right-of-Way acquisition will not be completed in time to advertise in FY25. The City of Glendale is aware that the FY25 MAG Close Out funds will be lost since the project will not be advertised by 09-30-2025.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation