PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 10/6/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/29/2021 2:39:01 PM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
N. OF NOTHING - S. OF SR 97 PAVEMENT REHABILITATION YG1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
93 Mohave 144.0 F038701C 12.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $29,977,000 17. Original Program Item #: 101680
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$29,977,000 ($29,977,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 29977 Item #:101680 ( ) FY:0 FundSRC: Desc: $ -29977 Item #:72323 (.) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year: 24  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 7/22/2022 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Project
26. JUSTIFICATION
Project is being deferred to FY24, to fully fund the I-17 Flex Lane improvement project.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/27/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2021 10:31:40 AM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
N. OF NOTHING - S. OF SR 97 PAVEMENT REHABILITATION YG1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 93 Mohave 144.0 F038701C 12.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $21,242,000 17. Original Program Item #: 101680
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$21,242,000 $8,735,000 (0%) $29,977,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 21242 Item #:101680 ( ) FY:0 FundSRC: Desc: $ 8735 Item #:72523 (.) FY:2023 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase construction budget.
26. JUSTIFICATION
The estimate used for programming was prepared in 2019 and did not include contingency for unidentified items and cost for the year of expenditure. The updated construction estimate for FY23 expenditure includes contingency for unidentified items and cost for the year of expenditure. ICAP is included in this request. Contingent upon PPAC approval, this will be included in the FY22-FY26 Five Year Program.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/20/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/21/2021 8:43:54 AM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
S.OF NOTHING - S. OF SR 97 PAVEMENT REHABILITATION YG1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 93 Mohave 144.0 F038701D 12.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $430,000 17. Original Program Item #: 101680
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$430,000 $0 (0%) $430,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 430 Item #:101680 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project.
26. JUSTIFICATION
As per the Pavement Management performance measure completed in 2019, the existing pavement has experienced distress cracking and is in substandard condition. The project will rehabilitate the existing pavement as recommended in the Planning Level Pre-scoping document. The design of this ADOT in-house project is programmed in FY21 with construction programmed in FY23. Request to change project name to "N.OF NOTHING - S. OF SR 97". Staff: $320K Consultant: $70K ICAP: $39K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox