PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 7/15/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
7/17/2025 11:17:41 AM | Patrick O`Leske | (480) 416-8367 | 205 S 17TH AVE |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 101L - I-10 | CONSTRUCT GPL | YD1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 202 | Maricopa | 50.6 | F084701D | 5.4 |
16. Original Program Budget: $5,626,000 | 17. Original Program Item #: 101557 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$5,626,000 | $0 (0%) | $5,626,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5626 Item #:101557 ( ($5,626,278)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This request is to establish the design phase to construct general-purpose lanes in both directions on SR202 (San Tan) between SR101 and I-10, as well as the design of a proposed northbound on-ramp for SR101 at Frye Road (CHN-RTP-079) as requested by MAG. MAG TIP #39473 Staff $154K Consultant $6,200K ICAP $413K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
Arizona Department of Transportation |