PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/14/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/30/2022 7:28:14 AM Joan Lovell (602) 712-7754 1615 W Jackson St, , PM02
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
LOOP 202 REGIONWIDE INSTALL WRONG WAY CAMERAS YB1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 202L Maricopa 0.1 F048501X 78 202-A(208)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $340,000 17. Original Program Item #: 101797
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$340,000 $0 (0%) $340,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 20 Item #:78822 (.) FY:2022 FundSRC:. Desc:TSM&O $ -20 Item #:79922 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 22 21a. Fiscal Year: 23  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer project to FY23
26. JUSTIFICATION
The increase in scope required more time to calculate the optimal placement of the wrong-way detection Cameras than anticipated. The information for optimal placement will establish the location the equipment will be installed. That documentation will be submitted so the clearances can be obtained. This is a Procurement Project, to be installed by ADOT forces.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/26/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/9/2022 3:16:28 PM Joan Lovell (602) 712-7754 1615 W Jackson St, , PM02
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Loop 202 Regionwide Install Wrong-way Cameras YB1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 202L Maricopa 0.1 F048501X 78 202-A(208)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101797
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $340,000 (0%) $340,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 320 Item #:OTHR22 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 22  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Project
26. JUSTIFICATION
This request is to install wrong-way equipment on Loop 202, Equipment will be purchased through Procurement. ICAP is included in this request. Contingent upon approval by MAG Regional Council on May 25, 2022. MAG TIP ID DOT 22-833.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval. Contingent upon approval by MAG Regional Council on May 25, 2022.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation