| PRB Meeting Date: 6/9/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 6/15/2026 11:44:49 AM | Derek Boland | (480) 796-4549 | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SELIGMAN TI - MP 132 | PAVEMENT REHABILITATION | XU1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 40 | Yavapai | 123.1 | F084801D | 8.9 | |
| 16. Original Program Budget: $610,000 | 17. Original Program Item #: 105290 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $610,000 | $91,000 (0%) | $701,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 610 Item #:72725 (100pct State) FY:0 FundSRC: Desc: | $ 91 Item #:72726 (100pct State) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 28 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. |
| 26. JUSTIFICATION |
| Funding is needed to design headwall rehab at a 144" multi plate pipe @ MP 127.45. This work was identified in the Planning Level Scoping Document and the rehab was verified through a site visit. Box culvert extensions are also needed to improve I-40 resiliency at MP 129.71. This work was not included in the PLS document but was identified to be needed during a site visit. Additionally, several of the existing light poles do not meet current ADOT standards. Roadway lighting at the Seligman TI intersection will be upgraded to current standards. The EB off-ramp right turn lane turning radius, will be improved to accommodate truck traffic. Staff $10k Consultant $75k ICAP $6k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 4/29/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/30/2025 2:37:19 PM | Rashidul Haque | (602) 712-7352 | 205 S 17TH AVE, 295, 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SELIGMAN TI - MP 132 | PAVEMENT REHABILITATION | XU1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 40 | Yavapai | 123.1 | F084801D | 8.9 | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 105290 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $610,000 (0%) | $610,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 610 Item #:72725 (100pct State) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This is a Pavement Rehabilitation Project on I-40 from Seligman TI - MP 132. Staff $100K Consultant $465K ICAP $45K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |