PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/9/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/15/2026 11:44:49 AM Derek Boland (480) 796-4549 , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SELIGMAN TI - MP 132 PAVEMENT REHABILITATION XU1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 40 Yavapai 123.1 F084801D 8.9  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $610,000 17. Original Program Item #: 105290
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$610,000 $91,000 (0%) $701,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 610 Item #:72725 (100pct State) FY:0 FundSRC: Desc: $ 91 Item #:72726 (100pct State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 28 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget.
26. JUSTIFICATION
Funding is needed to design headwall rehab at a 144" multi plate pipe @ MP 127.45. This work was identified in the Planning Level Scoping Document and the rehab was verified through a site visit. Box culvert extensions are also needed to improve I-40 resiliency at MP 129.71. This work was not included in the PLS document but was identified to be needed during a site visit. Additionally, several of the existing light poles do not meet current ADOT standards. Roadway lighting at the Seligman TI intersection will be upgraded to current standards. The EB off-ramp right turn lane turning radius, will be improved to accommodate truck traffic. Staff $10k Consultant $75k ICAP $6k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 4/29/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/30/2025 2:37:19 PM Rashidul Haque (602) 712-7352 205 S 17TH AVE, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SELIGMAN TI - MP 132 PAVEMENT REHABILITATION XU1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 40 Yavapai 123.1 F084801D 8.9  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 105290
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $610,000 (0%) $610,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 610 Item #:72725 (100pct State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This is a Pavement Rehabilitation Project on I-40 from Seligman TI - MP 132. Staff $100K Consultant $465K ICAP $45K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation