PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 4/25/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/17/2023 7:53:27 AM | Judah Cain | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 277 - FOREST SERVICE BDRY | PAVEMENT PRESERVATION | XR1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 377 | Navajo | 0.0 | F050601C | 6.4 | 377-A(201)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 103292 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $3,000,000 (0%) | $3,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 3000 Item #:72523 ( ) FY:2023 FundSRC:. Desc:PRESERVATION | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 23 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | 6/1/2023 | ||
| 25. DESCRIPTION OF REQUEST |
| Establish new project |
| 26. JUSTIFICATION |
| This pavement life extension project will mill the existing friction course and replace it with a hot applied chip-seal coat and micro-surfacing. The work also includes spot repair, pavement marking, and other related work. ICAP is included in the request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 8/16/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 8/18/2022 2:11:23 PM | Shantala Ramaiah |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 277 - Forest Service Bdry | PAVEMENT REHABLITATION | XR1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 377 | Navajo | 0 | F050601D | 6.4 | 377-A(201)T |
| 16. Original Program Budget: $180,000 | 17. Original Program Item #: 103292 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $180,000 | $0 (0%) | $180,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 180 Item #:72522 ( ) FY:2022 FundSRC:. Desc:PRESERVATION | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Update project scope and type of work. |
| 26. JUSTIFICATION |
| The ADOT Pavement Life Extension standard work was reclassified as Pavement Preservation. The project will not address deficient guardrail and barrier since it is a pavement preservation project. This is Minor & Preventative Pavement Subprogram project. Construction is planned for 3rd Quarter of FY23. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in Scope. Change in Work Type. | Item(s) Approved. |
| PRB Meeting Date: 4/26/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 6/6/2022 2:42:27 PM | Shantala Ramaiah |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SR 277 - Forest Service Bdry | PAVEMENT REHABILITATION | XR1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 377 | Navajo | 0 | F050601D | 6.4 | 377-A(201)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 103292 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $180,000 (0%) | $180,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 180 Item #:72522 (.) FY:2022 FundSRC:. Desc:PRESERVATION | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. |
| 26. JUSTIFICATION |
| The existing pavement is in substandard condition and needs rehabilitation. This project will construct spot repairs and address non-compliant ADA features and deficient guardrail, as needed. Construction is currently planned to come out of the Minor & Preventative Pavement Subprogram in FY23. Consultant: $129k Staff: $35k ICAP: $16k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |