PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 6/4/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/6/2024 8:46:44 AM | Angela Galietti | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
APACHE TRAIL & SUPERSTITION BLVD | STREET LIGHTING IMPROVEMENTS | XP1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 0000 | Pinal | APJ | T036501C | 0.0 | HSIPAPJ-0(220)T |
16. Original Program Budget: $2,016,000 | 17. Original Program Item #: 102010 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$2,016,000 | $96,000 (0%) | $2,112,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 22-0008647-I |
$ 2016 Item #:70124 (100pct VRU) FY:2024 FundSRC:. Desc:MODERNIZATION | $ 96 Item #:70124 (100pct VRU) FY:2024 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 24 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 6/28/2024 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget. |
26. JUSTIFICATION |
This is an HSIP project to install street lighting along Apache Trail from Palo Verde Drive to SR88 and along Superstition Boulevard from Meridian Drive to SR88. Budget increase due to unit cost increases in poles, foundations and mast arms. Contingent upon the LPA executing an updated JPA prior to the June Transportation Board meeting. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 10/18/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/20/2022 1:42:05 PM | Angela Galietti | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
APACHE TRAIL & SUPERSTITION BLVD | STREET LIGHTING IMPROVEMENTS | XP1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 0000 | Pinal | APJ | T036501D | 0.0 | HSIPAPJ-0(220)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 102010 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $30,000 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 22-0008647-I |
$ 30 Item #:OTHR23 (PDA Fee, 100pct Local) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project. |
26. JUSTIFICATION |
This is an HSIP project to install street lighting along Apache Trail from Palo Verde Drive to SR88 and along Superstition Boulevard from Meridian Drive to SR88. Staff - $30K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 10/18/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/20/2022 1:42:27 PM | Angela Galietti | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
APACHE TRAIL & SUPERSTITION BLVD | STREET LIGHTING IMPROVEMENTS | XP1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 0000 | Pinal | APJ | T036503D | 0.0 | HSIPAPJ-0(220)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 102010 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $420,000 (0%) | $420,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 22-0008647-I |
$ 420 Item #:102010 (100pct HSIP Design) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project. |
26. JUSTIFICATION |
This is an HSIP project to install street lighting along Apache Trail from Palo Verde Drive to SR88 and along Superstition Boulevard from Meridian Drive to SR88. Consultant - $420K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |