PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 2/27/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/1/2024 10:22:59 AM Chris Moore (602) 712-2132 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PORT OF ENTRY - I-10 INSTALL CCTV, DMS & WWD DEVICES XL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 19 Santa Cruz 0 F051401C 63 019-A(244)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,925,000 17. Original Program Item #: 103293
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,925,000 $1,992,000 (0%) $5,917,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 3925 Item #:103293 ( ) FY:0 FundSRC: Desc: $ 1992 Item #:79024 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 24 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/27/2024 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget, change project limits.
26. JUSTIFICATION
Project will install Dynamic Message Signs (DMS), Close-circuit Television (CCTV), and Wrong Way Driving (WWD) devices on I-19. Change Project Limits to: MP 2.48 to MP 57.19, and decrease Project Length to 54.71 miles. The design phase was initially established with a length of 63 miles. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 2/27/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/1/2024 10:22:04 AM Chris Moore (602) 712-2132 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PORT OF ENTRY - I-10 INSTALL CCTV, DMS & WWD DEVICES XL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 19 Santa Cruz 0 F051401D 63 019-A(244)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $411,000 17. Original Program Item #: 103293
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$411,000 $17,000 (0%) $428,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 330 Item #:79022 ( ) FY:0 FundSRC: Desc: $ 17 Item #:79024 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget. Change project length and limits.
26. JUSTIFICATION
Request budget increase to pay for UPRR permit fees required to attach an electrical service conduit to the I-19 Pima Mine Road/UPRR overpass. Additional utility and railroad coordination is required. Change Project Limits to MP 2.48 to 57.19, and decrease Project Length to 54.71 miles. The design phase was initially established with a length of 63.0 miles. UPRR Fees $7k Staff $8k ICAP $2k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 1/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/30/2024 1:55:00 PM Chris Moore (602) 712-2132 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PORT OF ENTRY - I-10 INSTALL CCTV, DMS & WWD DEVICES XL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 19 Santa Cruz 0 F051401C 63 019-A(244)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,925,000 17. Original Program Item #: 103293
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,925,000 $0 (0%) $3,925,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 3925 Item #:103293 ( ) FY:0 FundSRC: Desc: $ -3925 Item #:79024 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 24 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer project, change project limits.
26. JUSTIFICATION
Project will install Dynamic Message Signs (DMS), Close-circuit Television (CCTV), and Wrong Way Driving (WWD) devices on I-19. Request to move scheduled advertisement to FY25 Q2. Change Project Limits to: MP 2.48 to MP 63, and decrease Project Length to 54.71 miles. The design phase was initially established with a length of 63 miles. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Establish a New Project. Request Withdrawn.


PRB Meeting Date: 6/20/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/22/2023 9:12:25 AM Chris Moore (602) 712-2132 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PORT OF ENTRY - I-10 INSTALL CCTV, DMS & WWD DEVICES XL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 19 Santa Cruz 0 F051401D 63 019-A(244)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $330,000 17. Original Program Item #: 103293
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$330,000 $81,000 (0%) $411,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 330 Item #:79022 ( ) FY:0 FundSRC: Desc: $ 81 Item #:72323 (.) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change scope, increase budget.
26. JUSTIFICATION
Request budget increase to include connection of nine existing ITS devices to the broadband trunkline. Consultant $73k ICAP $8k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved.


PRB Meeting Date: 4/26/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/6/2022 2:35:54 PM Chris Moore (602) 712-2132 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PORT OF ENTRY - I-10 INSTALL CCTV, DMS & WWD DEVICES XL1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 19 Santa Cruz 0 F051401D 63  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103293
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $330,000 (0%) $330,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 330 Item #:79022 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project will install three DMS, three CCTV, four paired DMS/CCTV, and two WWD devices on I-19 from the Port of Entry to I-10/I-19 TI to improve traffic management. Staff $50k Consultant $248k ICAP $32k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox