PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/8/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/10/2025 10:39:05 AM Wesley Scatena (602) 712-8555 205 S 17TH AVE, , E741
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIORDAN BR - I-17 PAVEMENT REHABILITATION XH1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190 F084301D 5.5  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104998
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $670,000 (0%) $670,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 670 Item #:72725 (100pct State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish design project.
26. JUSTIFICATION
The Planning Level Scoping (PLS) document completed in September 2023 identifies milling asphaltic concrete from the mainline travel lanes and shoulders and replacing with stone matrix asphalt (SMA). The PLS also identifies mill and replace on ramps with SMA and on crossroads with AC-EP, for the traffic interchanges of: *I-17 / A-1 Mountain Rd *I-17 / SB-40 *I-17 / Flagstaff Ranch Rd Additional improvements include guardrail and fence replacement; drainage improvements; and bridge deck repair at 4 structures: *Flagstaff Ranch TI OP WB (Str No. 02020) *Flagstaff Ranch TI OP EB (Str No. 02027) *Woody Mountain Rd UP EB (Str No. 01132) *Woody Mountain Rd UP WB (Str No. 01133) Construction for this project is currently shown in FY 28 in the Tentative FY 26 - FY 30 Five Year Program. Staff: $140k Consultant: $477k ICAP: $53k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation