PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 9/1/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/3/2026 10:20:04 AM Wesley Scatena (602) 712-8555 205 S 17TH AVE, , E741
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
A-1 Mountain Rd - I-17 PAVEMENT REHABILITATION XH1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190.0 F084301C 5.5 NHPP040-C(232)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $32,363,000 17. Original Program Item #: 104998
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$32,363,000 $53,940,000 (0%) $86,303,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 32363 Item #:104998 ( ) FY:0 FundSRC: Desc: $ 15330 Item #:76227 (FY 27 Bridge FP) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 27 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 11/26/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget and add Scope.
26. JUSTIFICATION
The project`s initial scope entailed milling and replacing asphaltic concrete on I-40 from A-1 Mountain Road to the I-17 System Traffic Interchange (TI), including all associated ramps and crossroads. To consolidate work within these same limits, the scope of Project F0772 is being added to this pavement rehabilitation project to include the replacement of the Riordan Bridges. To address localized deterioration on the bridge deck, a transition to CMAR delivery is being made to facilitate necessary immediate work. A budget increase is requested to fund interim deck spot remediation and the installation of structural falsework. This targeted construction will structurally secure the hole in the deck and erect temporary support framing underneath. These critical measures will stabilize the structure and keep the bridge safely operational until the full replacement work begins. A budget increase of $53.94 million is requested. This total includes $53.00 million to add the Project F0772 bridge replacement scope and $940,000 for the interim deck spot remediation and structural falsework. Change the type of work to "Pavement Rehabilitation & Replace Bridge".
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Change in Work Type. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/1/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/3/2026 10:20:20 AM Wesley Scatena (602) 712-8555 205 S 17TH AVE, , E741
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
A-1 MOUNTAIN RD - I-17 Pavement Rehabilitation XH1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190.0 F084301D 5.0 NHPP040-C(232)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $670,000 17. Original Program Item #: 104998
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$670,000 $1,525,000 (0%) $2,195,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 670 Item #:72725 ( 100pct State) FY:0 FundSRC: Desc: $ 1525 Item #:72727 (100pct State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 27 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 11/26/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget.
26. JUSTIFICATION
The project`s initial scope entailed milling and replacing asphaltic concrete on I-40 from the A-1 Mountain Road TI to the I-17 System TI, including all associated ramps and crossroads. To consolidate work within these same limits, the scope of Project F0772 is being added to this pavement rehabilitation project to include the replacement of the Riordan Bridges. To support the use of CMAR delivery and expedite the urgent deck remediation, additional design funding is requested for preconstruction services and an independent cost estimate. Change the type of work to "Pavement Rehabilitation & Replace Bridge". Precon Services: $1,280k Consultant: $80k ADOT Staff: $77k ICAP: $88k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Change in Work Type. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 6/2/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/12/2026 1:12:03 PM Wesley Scatena (602) 712-8555 205 S 17TH AVE, , E741
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIORDAN BR - I-17 PAVEMENT REHABILITATION XH1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190.0 F084301C 5.5 NHPP040-C(232)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $32,363,000 17. Original Program Item #: 104998
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$32,363,000 $0 (0%) $32,363,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 32363 Item #:104998 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 27 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 11/26/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Project Name Change.
26. JUSTIFICATION
This request is to change the project name to "A-1 Mountain Rd - I-17" to more closely align with the project limits.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Item(s) Approved.


PRB Meeting Date: 4/8/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/10/2025 10:39:05 AM Wesley Scatena (602) 712-8555 205 S 17TH AVE, , E741
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIORDAN BR - I-17 PAVEMENT REHABILITATION XH1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190 F084301D 5.5  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104998
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $670,000 (0%) $670,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 670 Item #:72725 (100pct State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish design project.
26. JUSTIFICATION
The Planning Level Scoping (PLS) document completed in September 2023 identifies milling asphaltic concrete from the mainline travel lanes and shoulders and replacing with stone matrix asphalt (SMA). The PLS also identifies mill and replace on ramps with SMA and on crossroads with AC-EP, for the traffic interchanges of: *I-17 / A-1 Mountain Rd *I-17 / SB-40 *I-17 / Flagstaff Ranch Rd Additional improvements include guardrail and fence replacement; drainage improvements; and bridge deck repair at 4 structures: *Flagstaff Ranch TI OP WB (Str No. 02020) *Flagstaff Ranch TI OP EB (Str No. 02027) *Woody Mountain Rd UP EB (Str No. 01132) *Woody Mountain Rd UP WB (Str No. 01133) Construction for this project is currently shown in FY 28 in the Tentative FY 26 - FY 30 Five Year Program. Staff: $140k Consultant: $477k ICAP: $53k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox