PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/19/2024 9:01:48 AM Rashidul Haque (602) 712-7352 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
97TH AVE - 67th AVE DESIGN NEW FREEWAY XF1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 109.2 F050401D 4.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,000 17. Original Program Item #: 103174
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,000 $9,545,000 (0%) $9,548,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 12000 Item #:49922 ( ) FY:0 FundSRC: Desc: $ 9545 Item #:49924 (100pct RARF) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget. Change Project Limits. Change Project Length. Change Project Name.
26. JUSTIFICATION
This request is to fund the final design of the 97th Ave -71st Ave project. Change Project Limits to ending MP 112.2. Change Project Length to 3 miles. Change Project Name to 97th Ave-71st Ave. Approved by MAG at it`s 11/23/2023 Regional Council Meeting. MAG TIP DOT24-213. Consultant: $ 8,000K Staff: $622K ICAP:$923K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Item(s) Approved.


PRB Meeting Date: 2/21/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/23/2023 8:36:52 AM Kirstin Huston (602) 712-2167 205 S 17th Ave
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
97TH AVE - 67TH AVE DESIGN NEW FREEWAY XF1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 109.2 F050401D 4.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $12,000,000 17. Original Program Item #: 103174
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$12,000,000 ($11,997,000) (0%) $3,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 12000 Item #:49922 ( ) FY:0 FundSRC: Desc: $ -11997 Item #:49923 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Decrease budget
26. JUSTIFICATION
Project to be reprioritized and put on hold. Funds to be returned to RARF Contingency.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/5/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/14/2023 2:34:10 PM Kirstin Huston (602) 712-2167 205 S 17th Ave
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
97TH AVE - 67TH AVE DESIGN NEW FREEWAY XF1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 30 Maricopa 109.2 F050401D 4.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103174
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $12,000,000 (0%) $12,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 12000 Item #:49922 (FY22 Design) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This project will design State Route (SR) 30 from 67th Avenue to 97th Avenue. Project includes three new general purpose lanes in each direction with 50-foot wide open graded median with cable barriers, and full TIs at 83rd Avenue, and 91st Avenue. Funding was approved at Maricopa Association of Governments Regional Council on February 23, 2022. DOT 22-201D. Consultant $9,900K Staff: $960K ICAP: $1,140K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox