PRB Meeting Date: 7/7/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/9/2026 1:53:54 PM Alyssa Young (480) 932-9468 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PALOMA RD - SR 85 PAVEMENT REHABILITATION XD1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 8 Maricopa 106.0 F083701D 9.1 NHPP008-A(242)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $800,000 17. Original Program Item #: 105119
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$800,000 $200,000 (0%) $1,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 800 Item #:72725 (100pct state ) FY:0 FundSRC: Desc: $ 200 Item #:72727 (100pct state funds) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 28 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 8/10/2027 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget. Add Scope.
26. JUSTIFICATION
During field review, it was discovered that the pavement on Business Route 8, along the current project limits, has poor condition and needs resurfacing. This ADOT maintained route incurs heavy daily traffic and the construction district requested that this pavement be addressed with this project. The roadwork begins at the exit 115 and is approximately 1 mile worth of work. This will add roughly 1.5 million to the project construction. Additionally, the currently executed design contract amount is higher than what was originally estimated. This request also includes additional design funds needed due to this difference. Staff: $123K Consultant: $65K Icap: $12K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved.


PRB Meeting Date: 4/8/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/10/2025 10:39:31 AM Pedram Shafieian (602) 712-8166 205 S 17TH AVE, , 068R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
PALOMA RD - SR 85 PAVEMENT REHABILITATION XD1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 8 Maricopa 106.0 F083701D 9.1  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 105119
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $800,000 (0%) $800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 800 Item #:72725 (100pct State ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
ESTABLISH A NEW PROJECT
26. JUSTIFICATION
This project is pavement rehabilitation of Interstate 8 from Milepost 106 to Milepost 115 for about 9 miles. Staff $144k Consultant $597k ICAP $59k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation