PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/8/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/10/2025 10:38:30 AM Maie Elkeshky 480-330-4147 1615 W JACKSON ST, , 063R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 - BLAKE RANCH RD PAVEMENT REHABILITATION XC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 93 Mohave 90.8 F083901D 15.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 105002
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $670,000 (0%) $670,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 670 Item #:72725 (100pct State) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This is a Pavement Rehabilitation Project on US 93, from I-40 to Blake Ranch Rd (MP 90.8 to MP 106). Staff $481K Consultant $140K ICAP $49K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox