PRB Meeting Date: 4/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/25/2024 11:51:29 AM Pedram Shafieian (602) 712-8166 205 S 17th Ave, , 068R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WICKENBURG RANCH WAY - SR89 CONSTRUCT DIVIDED HIGHWAY XC1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 93 Yavapai 194.2 F012501C 1.3 093-B-NFA
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 100957
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $8,518,000 (0%) $8,518,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 16-0005960-I
$ 8518 Item #:OTHR28 (Developer Funded) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 28  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish construction project.
26. JUSTIFICATION
This developer funded project will construct roadway widening along US93 between Wickenburg Ranch Way and SR89 and a roundabout at the intersection of SR89. ICAP is not included in this project. The balance of the needed construction funding is being pursued by applying for a grant. The construction is planned in FY28.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 7/21/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/29/2020 8:06:48 AM Craig Regulski (602) 769-5585 2501 W Georgia Ave, , E748
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WICKENBURG RANCH WAY - SR89 CONSTRUCT DIVIDED HIGHWAY XC1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 93 Yavapai 194.2 F012501C 1.3 093-B(217)Z
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 100957
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $8,590,000 (0%) $8,590,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 16-0005960-I
$ 8590 Item #:OTHR21 (Developer Funded) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 21  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 7/31/2020 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 8/28/2020

25. DESCRIPTION OF REQUEST
Establish construction project.
26. JUSTIFICATION
This developer funded project will construct roadway widening along US93 between Wickenburg Ranch Way and SR89 and a roundabout at the intersection of SR89. ICAP is not included in this project.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 10/8/2019
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/5/2019 10:10:49 AM Craig Regulski (602) 769-5585 2501 W Georgia Ave, , E748
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WICKENBURG RANCH WAY - SR89 CONSTRUCT DIVIDED HIGHWAY XC1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 93 Yavapai 194.2 F012501C 1.3 093-B(217)Z
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 100957
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $8,515,000 (0%) $8,515,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 16-0005960-I
$ 8515 Item #:OTHR20 (Developer Funded) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 20  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 11/15/2019 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 12/13/2019

25. DESCRIPTION OF REQUEST
Establish construction project.
26. JUSTIFICATION
This developer funded project will construct roadway widening along US93 between Wickenburg Ranch Way and SR89 and a roundabout at the intersection of SR89. ICAP is not included in this project.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 11/20/2018
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/30/2019 10:32:06 AM Craig Regulski (602) 769-5585 2501 W Georgia Ave, , E748
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Wickenburg Ranch Way - SR89 Design Divided Highway XC1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 93 Yavapai 194.20 F012501D 1.27  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 100957
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $117,000 (0%) $117,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 16-0005960-1
$ 117 Item #:79919 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish project.
26. JUSTIFICATION
The project scope includes constructing a two lane divided highway from Wickenburg Ranch Way to SR89 with a roundabout at the intersection of SR89 and US93. The M3 developer will contribute a total of $9.81 million for design and construction of this project with any remaining funds allocated to the adjacent segment from Tegner St to Wickenburg Ranch Way. Since contribution is not made until completion of project design, non federal funding is requested for stage submittal review, issuing clearances, and project advertisement. Staff $66K Consultant $40K ICAP $11K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.