PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 3/22/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/24/2022 8:53:28 AM Rashidul Haque (602) 712-7352 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
67th Ave and 59 Ave TIs Traffic Interchange Improvements WZ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 101 Maricopa 18 F048901L 1  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103051
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $50,000 (0%) $50,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 50 Item #: 4271 (MAG REGIONWIDE - Preliminary Engineering (ADOT Staff)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project.
26. JUSTIFICATION
The purpose of this MAG project is to develop Project Assessment(PA) outlining improvements to the 67th Ave and 59th Ave traffic interchanges. This request provides funding for ADOT staff to participate in the meetings and to review the scoping document. This request was approved at the 01/26/22 MAG Regional Council Meeting (TIP ID : DOT22-201L). Staff : $45K ICAP: $5K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation