PRB Meeting Date: 3/8/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (520) 388-4231 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/6/2022 2:07:32 PM | James Gomes | (520) 388-4231 | 1221 S 2nd Ave, , T100 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
TANGERINE RD - ALVERNON WAY | Upgrade Traffic Signal Equipment | VW1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pima | 240 | F049201X | 24 | 010-D(225)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 102991 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $112,000 (0%) | $112,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 112 Item #:80607 (PAG RTA STBGP funds ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 22 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The South Central Traffic Operations (Unit 6543) requests to upgrade 5 TS-1 traffic signal cabinets with TS-2, Type 1 cabinets and controllers along I-10 within Pima County. This Project will utilize PAG RTA STBGP funds TIP ID 3.22 to purchase traffic signal equipment to upgrade to current standards. There is a 100pct federal contribution, no local match needed. The Project locations include I-10 at Tangerine, at Irvington, at Palo Verde, at Alvernon, and SR 86 at Camino De Oeste. The Project will utilize ADOT manpower to remove the existing traffic signal cabinets and replace with the new TS-2, Type 1 cabinets and controller at the 5 locations. This is a Procurement project. ICAP is included in the project estimate. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |