6. Project Name/Location: 7. Type of Work: 8. CPS Id:
TANGERINE RD - ALVERNON WAY Upgrade Traffic Signal Equipment VW1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pima 240 F049201X 24 010-D(225)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102991
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $112,000 (0%) $112,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 112 Item #:80607 (PAG RTA STBGP funds ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 22  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project
26. JUSTIFICATION
The South Central Traffic Operations (Unit 6543) requests to upgrade 5 TS-1 traffic signal cabinets with TS-2, Type 1 cabinets and controllers along I-10 within Pima County. This Project will utilize PAG RTA STBGP funds TIP ID 3.22 to purchase traffic signal equipment to upgrade to current standards. There is a 100pct federal contribution, no local match needed. The Project locations include I-10 at Tangerine, at Irvington, at Palo Verde, at Alvernon, and SR 86 at Camino De Oeste. The Project will utilize ADOT manpower to remove the existing traffic signal cabinets and replace with the new TS-2, Type 1 cabinets and controller at the 5 locations. This is a Procurement project. ICAP is included in the project estimate.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.