PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/28/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/13/2026 10:29:22 AM Wesley Scatena (602) 712-8555 205 S 17TH AVE, , E741
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RED ROCK TI UP BRIDGE REHABILITATION VU1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 226.4 F049701D 1.0 NHPP
PROJECT REQUEST SUMMARY
16. Original Program Budget: $600,000 17. Original Program Item #: 102926
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$600,000 $0 (0%) $600,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 600 Item #:102926 (Fed funds + state match) FY:0 FundSRC: Desc: $ -600 Item #:76227 (Fed funds + state match) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Advance Design from FY27 to FY26.
26. JUSTIFICATION
This is a bridge rehabilitation project on I-10 at the Red Rock TI UP in Southcentral District. Staff: $565K ICAP: $35K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation