PRB Meeting Date: 4/7/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/20/2026 9:59:42 AM Chris Rodriguez (602) 712-4642 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER RD: RECKER RD - POWER RD IMPROVE ROADWAY VK1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa GIL T033501C 0.0 STBGGIL-0(219)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,325,000 17. Original Program Item #: 102826
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,325,000 $0 (0%) $10,325,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008465-I
$ 10325 Item #:102826 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 5/20/2026 22a. Bid Pkg Rdy Date: 5/1/2027 24. Verified all of the new funding sources
23. Bid Adv Date: 6/20/2026 23a. Bid Adv Date: 6/10/2027

25. DESCRIPTION OF REQUEST
Defer Project from FY 2026 to FY 2027.
26. JUSTIFICATION
Town of Gilbert needs to acquire Right of Way for the project. This will not be done till late calendar year 2026 or early 2027. Request to change construction advertisement from FY 2026 to Q4 FY2027.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Request Withdrawn.