PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/23/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/26/2026 1:25:20 PM Chris Rodriguez (602) 712-4642 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER RD: RECKER RD - POWER RD IMPROVE ROADWAY VK1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa GIL T033501R 0.0 STBGGIL-0(219)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,450,000 17. Original Program Item #: 102826
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,450,000 $0 (0%) $2,450,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008465-I
$ 2450 Item #:OTHR26 (CMAQ $2,450,000 for right-of-way acquisition. ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 5/20/2026 22a. Bid Pkg Rdy Date: 3/1/2027 24. Verified all of the new funding sources
23. Bid Adv Date: 6/20/2026 23a. Bid Adv Date: 4/1/2027

25. DESCRIPTION OF REQUEST
Establish Right of Way subphase.
26. JUSTIFICATION
The project requires the Town of Gilbert to acquire new Right of Way for construction. The Right of Way costs include reimbursement using federal funds, local match and additional local contribution. This request is to have reimbursement portion of the funds available for the acquisition of new Right of Way.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 6/9/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/15/2026 11:46:40 AM Chris Rodriguez (602) 712-4642 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER RD: RECKER RD - POWER RD IMPROVE ROADWAY VK1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa GIL T033501C 0.0 STBGGIL-0(219)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,325,000 17. Original Program Item #: 102826
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,325,000 $0 (0%) $10,325,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008465-I
$ 10325 Item #:102826 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 5/20/2026 22a. Bid Pkg Rdy Date: 3/1/2027 24. Verified all of the new funding sources
23. Bid Adv Date: 6/20/2026 23a. Bid Adv Date: 4/1/2027

25. DESCRIPTION OF REQUEST
Defer Project from FY 2026 to FY 2027.
26. JUSTIFICATION
Town of Gilbert needs to acquire Right of Way for the project. This will not be done until late calendar year 2026 or early 2027. Request to change construction advertisement from FY 2026 to Q4 FY 27. The town of Gilbert has updated this project in their TIP. This action is contingent upon MAG Regional Council approval in June.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.


PRB Meeting Date: 4/7/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/20/2026 9:59:42 AM Chris Rodriguez (602) 712-4642 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
WARNER RD: RECKER RD - POWER RD IMPROVE ROADWAY VK1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 0000 Maricopa GIL T033501C 0.0 STBGGIL-0(219)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,325,000 17. Original Program Item #: 102826
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,325,000 $0 (0%) $10,325,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-0008465-I
$ 10325 Item #:102826 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 5/20/2026 22a. Bid Pkg Rdy Date: 5/1/2027 24. Verified all of the new funding sources
23. Bid Adv Date: 6/20/2026 23a. Bid Adv Date: 6/10/2027

25. DESCRIPTION OF REQUEST
Defer Project from FY 2026 to FY 2027.
26. JUSTIFICATION
Town of Gilbert needs to acquire Right of Way for the project. This will not be done till late calendar year 2026 or early 2027. Request to change construction advertisement from FY 2026 to Q4 FY2027.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Request Withdrawn.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation