PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 3/10/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/10/2026 11:11:47 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601D | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $5,300,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $5,300,000 | $2,000,000 (0%) | $7,300,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 5000 Item #:DT56330 (State Legislative Appropriation Funds) FY:0 FundSRC: Desc: | $ 2000 Item #:49926 (100pct RARF) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. Requesting additional funds to cover pre-construction expenses needed for the CMAR delivery. Contingent upon MAG Regional Council approval. Staff: $50K Consultant: $1.835M ICAP: $115K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 3/10/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/13/2026 2:16:07 PM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601C | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $80,469,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $80,469,000 | ($2,000,000) (0%) | $78,469,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 38278 Item #:102988 ($38,277,977) FY:0 FundSRC: Desc: | $ -2000 Item #:49926 (100pct RARF) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Decrease Budget. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. This request decreases construction funding. Contingent upon MAG Regional Council approval. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 2/24/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/13/2026 2:42:15 PM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601C | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $38,278,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $38,278,000 | $42,191,000 (0%) | $80,469,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 38278 Item #:102988 ($38,277,977) FY:0 FundSRC: Desc: | $ -38278 Item #:49930 (RARF) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. Move Project from FY30 to FY26. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. This request is to match with MAG`s TIP actions approved in November 2025 and pending Regional Council 2/25/2026 meeting. Additionally, this request decreases construction funding by $300k. MAG ID is 15426 and TIP ID DOT30-505C. ICAP is included in this request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 2/24/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/13/2026 2:42:40 PM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601D | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $5,000,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $5,000,000 | $300,000 (0%) | $5,300,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 5000 Item #:DT56330 (State Legislative Appropriation Funds) FY:0 FundSRC: Desc: | $ 300 Item #:49926 (100pct RARF) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. Requesting additional design funds to cover part of the expenses needed to change the delivery to CMAR. Contingent upon MAG Regional Council approval at February meeting. MAG ID is 15426 and TIP ID DOT30-505C. Consultant: $282K ICAP: $18K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 1/6/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 1/8/2026 8:49:33 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601C | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $39,615,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $39,615,000 | $42,491,000 (0%) | $82,106,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 38278 Item #:102988 ($38,277,977) FY:0 FundSRC: Desc: | $ -38278 Item #:49930 (RARF) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. Move Project from FY30 to FY26. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. This request is to keep in sync with MAG`s TIP actions approved in November. MAG ID is 15426 and TIP ID DOT30-505C. ICAP is included in this request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Request Withdrawn. |
| PRB Meeting Date: 9/30/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/2/2025 10:29:02 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601X | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $2,000,000 (0%) | $2,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 2000 Item #:49926 (100pct RARF) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Sub-Phase. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. This request is to advance procurement of construction items, such as traffic signals at the traffic interchange only. MAG ID is 15426 and TIP ID DOT26-256P. Construction: $1,885,014 ICAP: $114,896 |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 9/30/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/2/2025 10:32:54 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601R | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $16,000,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $16,000,000 | $42,500,000 (0%) | $58,500,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 472 Item #:102988 (NHPP 94.34pct) FY:0 FundSRC: Desc: | $ 19000 Item #:102988 (NHPP (94.34pct)) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. |
| 26. JUSTIFICATION |
| Additional funds are needed for the right-of-way acquisition. The 5-year program was amended per MAG 2026-2030 FLCP/RTPFP rebalancing done in June 2025 to add additional funds. MAG ID is 15426 and TIP ID DOT26-256R. ROW: $40,056,550 ICAP: $2,443,450 |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 11/26/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 12/2/2024 9:44:54 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601R | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $16,000,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $16,000,000 | $0 (0%) | $16,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 472 Item #:102988 (NHPP 94.34pct) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Sub-Phase. |
| 26. JUSTIFICATION |
| The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. This request is to acquire four parcels at the TI only (502-36-025A; 502-36-029B; 502-36-036K; 502-36-036L). MAG ID is 15426 and TIP ID DOT25-256R. ROW: $14.828M ICAP: $1.172M |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 3/5/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/7/2024 2:03:59 PM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | Reconstruct Traffic Interchange | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601D | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $5,000,000 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $5,000,000 | $0 (0%) | $5,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 5000 Item #:DT56330 (State Legislative Appropriation Funds) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish a Design Project. |
| 26. JUSTIFICATION |
| Request funds for final design of the Jackrabbit Trail and I-10 traffic interchange improvements. The project will reconstruct the existing interchange and replace the existing bridges to accommodate a full tight diamond interchange. Additionally the project will widen the existing Jackrabbit Trail Roadway to a 6-lane roadway between McDowell Road and Van Buren Street. Project includes sidewalks, signalized intersections, utility designation/potholing, right-of-way, retention basins. Staff: $516K Consultant: $4.0Mil ICAP: $484K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 2/15/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 2/18/2022 8:45:55 AM | Olivier Mirza | , , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| JACKRABBIT TRAIL TI | SCOPING (DCR/Env Doc) | VF1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 10 | Maricopa | 122.0 | F048601L | 1.0 | 010-B(222)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 102988 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $1,500,000 (0%) | $1,500,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 1500 Item #:49922 (RARF Funding) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish a Scoping Project. |
| 26. JUSTIFICATION |
| Increased travel demand on Jackrabbit Trail has strained the capacity of the existing Jackrabbit Trail and I-10 traffic interchange. This study will evaluate traffic interchange alternatives at Jackrabbit Trail Rd and Interstate 10, including widening Jackrabbit Trail from McDowell Rd to Roosevelt St. The project will include the reconstruction/improvements at McDowell Rd and Roosevelt St. The study will include preparation of a Design Concept Report (DCR) and an Environmental Clearance document. The construction phase will be funded using Federal Aid, which is planned to be in FY26. MAG ID is 15426 and TIP ID DOT22-017D. Request to change design funding from Federal Aid to RARF will go to MAG Regional Council for approval on March 23, 2022. Staff: $200K Consultant: $1.157Mil ICAP: $143K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |