PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 8/22/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/18/2023 8:19:40 AM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601C 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $6,200,000 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$6,200,000 $1,085,000 (0%) $7,285,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219, 22-8745
$ 2100 Item #:73323 ( ) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS $ 537 Item #:OTHR24 ( JPA 21-8219 City of Maricopa funding for 49.5pct of construction need) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/20/2023 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
Add money to the construction budget to fully fund the contractor`s bid amount. The additional money is split 50.5pct ADOT and 49.5pct City. The requested change includes ICAP.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Contingent upon approval by MAG Regional Council in Sept. 2023


PRB Meeting Date: 8/8/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/18/2023 8:20:55 AM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601D 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $484,000 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$484,000 $15,000 (0%) $499,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219
$ 60 Item #:73323 (.) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS $ 15 Item #:73324 (.) FY:2024 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
Contractor discussions and preparation of justification document post-bid resulted in additional staff and PM time. Staff - $13k ICAP - $2k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 4/25/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/10/2023 7:23:21 AM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601C 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $6,200,000 (0%) $6,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219, 22-8745
$ 2100 Item #:73323 (Statewide Minor Projects per IGA 21-8219) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 23  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 6/20/2023

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This is a Central District Minor Programs Project in the City of Maricopa. The project scope is to widen the NB roadway from 2 to 3 lanes and rehabilitate the existing pavement in both directions, within the project limits. The Lakeview Drive/Cobblestone Farms Rd intersections are being widened to provide additional turning capacity onto SR 347. This will be a turnback to the City once the construction is complete. The pavement rehabilitation work is to be funded by the state per IGA (22-8745) and the original unit costs and quantities were underestimated. The local contribution has been received. Environmental clearance is planned for 4/26, with ROW and Utility clearance to follow shortly thereafter. There are no new ROW or utility conflicts on the project. Contingent upon approval by MAG Regional Council, anticipated in May, 2023. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/18/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/20/2023 8:11:23 AM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601D 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $428,000 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$428,000 $56,000 (0%) $484,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219
$ 60 Item #:73323 (.) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS $ 56 Item #:73323 (.) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
This project will result in a turnback of the roadway and ROW to the City of Maricopa. Additional work for the consultant is necessary to incorporate added pavement rehabilitation length, GRIC native plant inventory, and 404 technical report. Local coordination was underestimated for ADOT staff and consultant, resulting in multiple meetings related to the turnback. Consultant - $28k Staff - $22k ICAP - $6k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 2/14/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/16/2023 1:27:58 PM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601C 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $5,500,000 (0%) $5,500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219, 22-8745
$ 2055 Item #:73323 (Statewide Minor Projects per IGA 21-8219) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This is a Central District Minor Project in the City of Maricopa. The project scope is to widen the NB roadway to 3 lanes and rehabilitate the existing pavement in both directions, within the project limits. This will be a turnback to the City once the construction is complete. The pavement rehabilitation work is to be funded by the state per IGA (22-8745) and the original unit costs and quantities were underestimated. 10.5pct ICAP is included in the total amount.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
FYI/Guidance. Will return when we have local funds.


PRB Meeting Date: 8/2/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
8/2/2022 9:33:57 AM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601D 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $368,000 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$368,000 $60,000 (0%) $428,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219
$ 368 Item #:73322 ( ) FY:2022 FundSRC:. Desc:STATEWIDE MINOR PROJECTS $ 60 Item #:73323 ( ) FY:2023 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
Level of design effort required for project was underestimated at the time of initiation. Consultant $54K ICAP $6K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 4/26/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/6/2022 2:49:20 PM Trent Kelso (602) 723-8313 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR238 - MARICOPA CITY LIMITS WIDEN ROADWAY UT1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 174.0 F043601D 1.4 347-A(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103309
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $368,000 (0%) $368,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 21-8219
$ 368 Item #:73322 ( ) FY:2022 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Project
26. JUSTIFICATION
The project will improve the operational efficiency and safety of the Lakeview/Cobblestone Farms/SR 347 intersection by adding a 3rd northbound lane from SR238 to north of the City limits and an acceleration lane north of Lakeview Drive. The design includes survey and mapping, geotechnical investigations, Coordination with GRIC, Final PS&E documents, and preparation of the three clearance documents (ROW, Utilities, and Environmental). Staff: $50K Consultant: $283k ICAP: $35K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox