PRB Meeting Date: 12/17/2024
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/19/2024 11:36:36 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
EAST-WEST CORRIDOR; SR 347 - I-10 ENVIRONMENTAL REVIEW UI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 999 Pinal 0.0 M724701L 0.0 999-M(0)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104019
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $50,000 (0%) $50,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 24-0009772-I
$ 50 Item #:OTHR25 (100pct Pinal County) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish project.
26. JUSTIFICATION
Pinal County is completing final design of approximately 20 miles of the Arizona Parkway corridor improvements from the Ak-Chin Casino at SR 347 to a new traffic interchange at I-10 and Val Vista Drive. Pinal County has requested that ADOT provide environmental review and oversight of the project. This request is 100 percent funded by Pinal County. Staff - $50K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.