2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
11/21/2024 10:41:18 AM | Jane Gauger | 602-712-4052 | 205 S 17th Ave MD 618E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Fanning Drive @ BNSF, Flagstaff | Rail-Highway Safety Upgrade | TV1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 0000 | Coconino | 0 | T052801X | 0.1 | FLA-0(222)T |
16. Original Program Budget: $0 | 17. Original Program Item #: |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $1,050,000 (0%) | $1,050,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | IGA-24-0009570-I |
$ 1050 Item #:72625 (Section 130 FHWA 100 percent federal funding) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a new project. |
26. JUSTIFICATION |
This is a Section 130 Rail-Highway safety upgrade. This project will improve the safety at this railroad crossing. BNSF Railway will complete the safety upgrades, which consist of pedestrian gates, barrier fencing, additional lights, and signs. This crossing is a concern for the Federal Railroad Administration (FRA), who oversees all railroads in the U.S. There is a number of pedestrian incidents and recent pedestrian fatalities at this crossing. Construction of this project will help to reduce pedestrian incidents and fatalities. All 01X funding is 100 percent Section 130 federal funding. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 11/19/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
11/21/2024 10:41:03 AM | Jane Gauger | 602-712-4052 | 205 S 17th Ave, MD 618E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Fanning Dr @ BNSF, Flagstaff | Rail-Highway Safety Upgrade | TV1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 0000 | Coconino | 0 | T052801D | 0.1 | FLA-0(222)T |
16. Original Program Budget: $0 | 17. Original Program Item #: |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $150,000 (0%) | $150,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | IGA-24-0009570-I |
$ 150 Item #:72625 (Section 130 FHWA 100 percent federal funding) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a new project. |
26. JUSTIFICATION |
This is a Section 130 Rail-Highway safety upgrade. This project will improve the safety at this railroad crossing. BNSF Railway will complete the safety upgrades, which consist of pedestrian gates, barrier fencing, additional lights, and signs. This crossing is a concern for the Federal Railroad Administration (FRA), who oversees all railroads in the U.S. There is a number of pedestrian incidents and recent pedestrian fatalities at this crossing. Construction of this project will help to reduce pedestrian incidents and fatalities. All 01D funding is 100 percent Section 130 federal funding. ADOT- Oversight, coordination, clearances - $40K BNSF- Preliminary Engineering - $110K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |