PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SANTA MARIA RIVER BRIDGE BRIDGE REPLACEMENT TV1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 96 Yavapai 10.0 F058401D 1.0 STBG096-A(200)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $800,000 17. Original Program Item #: 100216
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$800,000 $609,000 (0%) $1,409,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 754 Item #: 100216 (STGBP Flex - Santa Maria River Bridge Deck Rehabilitation & Scour Retrofit ) FY:0 FundSRC: Desc: $ 609 Item #: 76224 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
This is a bridge replacement project of a scour vulnerable and fracture critical two girder system bridge with pin and hanger hinges. During final design it was determined that a detailed PA is needed to evaluate replacement alternatives. The PA recommended alternative requires new right-of-way and temporary construction easement. Requesting funds to cover the detailed PA effort, right-of-way appraisal and plans, additional geotech and environmental consultant costs. Staff: $250K Consultant: $300K ICAP: $59K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 2/21/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/23/2023 8:34:56 AM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SANTA MARIA RIVER BRIDGE DECK REHABILITATION & SCOUR RETROFIT TV1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 96 Yavapai 10.0 F058401D 1.0 STBG096-A(200)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $800,000 17. Original Program Item #: 100216
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$800,000 $0 (0%) $800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 754 Item #: 100216 (STGBP Flex - Santa Maria River Bridge Deck Rehabilitation & Scour Retrofit ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project. Change Type Of Work.
26. JUSTIFICATION
Based on the latest in-depth bridge inspection report, the existing bridge deck is deteriorating and the bridge is a fracture critical two girder system bridge with pin and hanger hinges. Given that this Bridge is also scour vulnerable, it is recommended that this be a bridge replacement. Request to change the Type Of Work to, "Bridge Replacement". Staff: $539K Consultant: $185K ICAP: $76K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Work Type. Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 11/8/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/10/2022 8:12:09 AM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SANTA MARIA RIVER BRIDGE DECK REHABILITATION & SCOUR RETROFIT TV1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 96 Yavapai 10.0 F058401D 1.0 STBG096-A(200)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $800,000 17. Original Program Item #: 100216
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$800,000 $0 (0%) $800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 754 Item #: 100216 (STGBP Flex - Santa Maria River Bridge Deck Rehabilitation & Scour Retrofit ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
Based on the latest in-depth bridge inspection report, the existing bridge deck is deteriorating and the bridge is a fracture critical two girder system bridge with pin and hanger hinges. Given that this Bridge is also scour vulnerable, it is recommended that this be a bridge replacement. Request to change the Type Of Work to, "Bridge Replacement". Staff: $539K Consultant: $185K ICAP: $76K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Work Type. Establish a New Project. Request Withdrawn. Pending Bridge Program Funding Assessment.