PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 2/11/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/13/2025 9:29:59 AM | Sal Salahuddin | (602) 712-7156 | 205 S 17th Ave, Phoenix, AZ 85007, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SILVER CREEK DR & SILVER LAKE BLVD CROSSINGS | REPLACE BRIDGE | TS1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 0000 | Navajo | NNA | T063301D | 0.0 |
16. Original Program Budget: $30,000 | 17. Original Program Item #: 104691 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$30,000 | $0 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0010896-I |
$ 30 Item #:73625 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project |
26. JUSTIFICATION |
This AZSMART grant project will provide design funding for the Navajo County safe and resilient crossings project. The project scope includes bridge replacement at Silver Creek Drive and a Storm Drain crossing at Silver Lake Boulevard, associated roadway improvements including sidewalks, crosswalks and ADA features. Staff: $30K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 2/11/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/13/2025 9:31:11 AM | Sal Salahuddin | (602) 712-7156 | 205 S 17th Ave, Phoenix, AZ 85007, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SILVER CREEK DR & SILVER LAKE BLVD CROSSINGS | REPLACE BRIDGE | TS1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 0000 | Navajo | NNA | T063303D | 0.0 |
16. Original Program Budget: $860,000 | 17. Original Program Item #: 104691 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$860,000 | $0 (0%) | $860,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0010896-I |
$ 860 Item #:73625 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish design project |
26. JUSTIFICATION |
This AZSMART grant project will provide design funding for the Navajo County safe and resilient crossings project. The project scope includes bridge replacement at Silver Creek Drive and a Storm Drain crossing at Silver Lake Boulevard, associated roadway improvements including sidewalks, crosswalks and ADA features. Consultant: $860K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |