PRB Meeting Date: 12/19/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/22/2023 8:42:09 AM Bharat Kandel (602) 712-8736 205 S 17th Ave, , EM01
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COYOTE WASH BRIDGE BRIDGE REPLACEMENT TO1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 87 Navajo 374.0 F031701D 1.0 STBG 087-D(205)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $604,000 17. Original Program Item #: 100244
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$604,000 $32,000 (0%) $636,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 604 Item #: 100244 (Coyote Wash Bridge - Bridge Rehabilitation) FY:0 FundSRC: Desc: $ 32 Item #: 76224 (BRIDGE REPLACEMENT & REHABILITATION) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
The project has been advertised. The actual hours especially on Bridge Design exceeded the originally estimated hours. The additional funds are requested to cover the current payroll rejects and staff charges. Staff - $29k ICAP - $3k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 4/21/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/9/2020 2:05:33 PM Bharat Kandel (602) 712-8736 205 S 17th Ave, , EM01
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
COYOTE WASH BRIDGE BRIDGE REPLACEMENT TO1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 87 Navajo 374.0 F031701D 1.0 STBG 087-D(205)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $750,000 17. Original Program Item #: 100244
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$750,000 ($146,000) (0%) $604,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 750 Item #: 100244 (Coyote Wash Bridge - Bridge Rehabilitation) FY:0 FundSRC: Desc: $ -146 Item #:76220 ( ) FY:2020 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This Bridge has more than 70 years under service. Existing Reinforced Concrete Deck top has extensive hairline, longitudinal, transverse and map cracks, several large, shallow delaminations including exposed rebar. Deck bottom has minor hairline transverse and random cracks and light efflorescence. Construction joints have patches, cracks , and spalls. Girders have some patched areas at the top plus leakage stains and minor efflorescence. Pier caps have hairline to narrow horizontal cracks. Abutments have hairline vertical cracks etc. Staff - $428k Consultant - $121k ICAP - $55k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox