6/7/2022 12:40:04 PM Angela Galietti (602) 712-7551 205 S 17th Ave, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN PEDRO RIVER BRIDGE STR NO. 0403 BRIDGE REHBILITATION TM1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 82 Cochise 61.2 F052201D 1 082-A(210)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $700,000 17. Original Program Item #: 100210
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$700,000 $0 (0%) $700,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #: 100210 (Bridge Replacement FY22) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project.
26. JUSTIFICATION
Based on discussion from the design team and bridge group, a bridge replacement is needed. The bridge was constructed in 1914 and lengthened in 1954 to mitigate scour concerns. The bridge has a sufficiency rating of 55.70 and is considered in Fair Condition. Consultant: $221K Staff: $368K ICAP: $66K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.