PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 1/14/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/22/2025 9:16:34 AM | Angela Galietti | (602) 712-7551 | 205 S 17th Ave, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SAN PEDRO RIVER BRIDGE STR NO. 0403 | BRIDGE REHABILITATION | TM1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 82 | Cochise | 61.2 | F052201C | 1.0 | STBG082-A(210)T |
16. Original Program Budget: $11,800,000 | 17. Original Program Item #: 100210 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$11,800,000 | $0 (0%) | $11,800,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 11800 Item #: 100210 ( ) FY:0 FundSRC: Desc: | $ 11800 Item #:76226 (.) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | 26 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 6/27/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer Advertisement to FY26 |
26. JUSTIFICATION |
This is a project to replace the existing SR82 bridge over the San Pedro River. Due to delays associated with early Geotechnical Clearance and Cultural Clearance, the project cannot be delivered in FY25. This changes will be included in the FY26 - FY30 Five Year Program |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 12/17/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/19/2024 12:13:36 PM | Angela Galietti | (602) 712-7551 | 205 S 17th Ave, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SAN PEDRO RIVER BRIDGE STR NO. 0403 | BRIDGE REHBILITATION | TM1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 82 | Cochise | 61.2 | F052201D | 1 | 082-A(210)T |
16. Original Program Budget: $700,000 | 17. Original Program Item #: 100210 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$700,000 | $356,000 (0%) | $1,056,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 700 Item #: 100210 (Bridge Replacement FY22) FY:0 FundSRC: Desc: | $ 356 Item #:76225 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget. |
26. JUSTIFICATION |
Increase in budget to accommodate additional work associated with Environmental Tasks and staff design costs that were higher than anticipated. Cultural sites and Biological constraints were identified during design development that required additional hours for Environmental Sub-Consultant and staff for coordination. Consultant: $154K Staff: $176K ICAP: $26K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 5/24/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/7/2022 12:40:04 PM | Angela Galietti | (602) 712-7551 | 205 S 17th Ave, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SAN PEDRO RIVER BRIDGE STR NO. 0403 | BRIDGE REHBILITATION | TM1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 82 | Cochise | 61.2 | F052201D | 1 | 082-A(210)T |
16. Original Program Budget: $700,000 | 17. Original Program Item #: 100210 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$700,000 | $0 (0%) | $700,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 700 Item #: 100210 (Bridge Replacement FY22) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new design project. |
26. JUSTIFICATION |
Based on discussion from the design team and bridge group, a bridge replacement is needed. The bridge was constructed in 1914 and lengthened in 1954 to mitigate scour concerns. The bridge has a sufficiency rating of 55.70 and is considered in Fair Condition. Consultant: $221K Staff: $368K ICAP: $66K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |