PRB Meeting Date: 1/14/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/22/2025 9:16:34 AM Angela Galietti (602) 712-7551 205 S 17th Ave, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN PEDRO RIVER BRIDGE STR NO. 0403 BRIDGE REHABILITATION TM1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 82 Cochise 61.2 F052201C 1.0 STBG082-A(210)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $11,800,000 17. Original Program Item #: 100210
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$11,800,000 $0 (0%) $11,800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 11800 Item #: 100210 ( ) FY:0 FundSRC: Desc: $ 11800 Item #:76226 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/27/2025 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Advertisement to FY26
26. JUSTIFICATION
This is a project to replace the existing SR82 bridge over the San Pedro River. Due to delays associated with early Geotechnical Clearance and Cultural Clearance, the project cannot be delivered in FY25. This changes will be included in the FY26 - FY30 Five Year Program
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 12/17/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/19/2024 12:13:36 PM Angela Galietti (602) 712-7551 205 S 17th Ave, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN PEDRO RIVER BRIDGE STR NO. 0403 BRIDGE REHBILITATION TM1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 82 Cochise 61.2 F052201D 1 082-A(210)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $700,000 17. Original Program Item #: 100210
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$700,000 $356,000 (0%) $1,056,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #: 100210 (Bridge Replacement FY22) FY:0 FundSRC: Desc: $ 356 Item #:76225 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget.
26. JUSTIFICATION
Increase in budget to accommodate additional work associated with Environmental Tasks and staff design costs that were higher than anticipated. Cultural sites and Biological constraints were identified during design development that required additional hours for Environmental Sub-Consultant and staff for coordination. Consultant: $154K Staff: $176K ICAP: $26K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 5/24/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/7/2022 12:40:04 PM Angela Galietti (602) 712-7551 205 S 17th Ave, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN PEDRO RIVER BRIDGE STR NO. 0403 BRIDGE REHBILITATION TM1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 82 Cochise 61.2 F052201D 1 082-A(210)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $700,000 17. Original Program Item #: 100210
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$700,000 $0 (0%) $700,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #: 100210 (Bridge Replacement FY22) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project.
26. JUSTIFICATION
Based on discussion from the design team and bridge group, a bridge replacement is needed. The bridge was constructed in 1914 and lengthened in 1954 to mitigate scour concerns. The bridge has a sufficiency rating of 55.70 and is considered in Fair Condition. Consultant: $221K Staff: $368K ICAP: $66K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.