PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 3/10/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/13/2026 11:46:31 AM | Wesley Scatena | (602) 712-8555 | 205 S 17TH AVE, , E741 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| SOUTH FLORENCE ST @ ASH AVENUE, CASA GRANDE | CONSTRUCT ROUNDABOUT | TA1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T061801C | 0.0 | CDS CSG-0(216)T |
| 16. Original Program Budget: $3,500,000 | 17. Original Program Item #: 104450 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $3,500,000 | $0 (0%) | $3,500,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009801-I |
| $ 2500 Item #:90000 (CDS Earmark) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | 27 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 9/16/2026 | 24. Verified all of the new funding sources | |
| 23. Bid Adv Date: | 4/14/2026 | 23a. Bid Adv Date: | 10/2/2026 | |
| 25. DESCRIPTION OF REQUEST |
| Defer Project to FY27. |
| 26. JUSTIFICATION |
| This project is currently programmed for construction in FY26. Funding source is CDS earmark available for obligation through September 30th, 2027. Additional time is needed for ROW acquisition and utility relocations. This request is to defer construction from FY26 to FY27 to advertise this project in Q2 FY27. SCMPO approved a TIP amendment to move construction to FY27 at their February 26th TAC meeting. The amendment will go to the SCMPO Executive Board on March 10th. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. Change in Schedule. | Item(s) Approved. |
| PRB Meeting Date: 6/24/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 6/25/2025 10:07:33 AM | Wesley Scatena | (602) 712-8555 | 205 S 17TH AVE, , E741 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CASA GRANDE ASH AVENUE ROUNDABOUT | CONSTRUCT ROUNDABOUT | TA1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T061801D | 0.0 | CDS CSG-0(216)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104450 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $45,000 (0%) | $45,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009573-I |
| $ 45 Item #:OTHR25 (Casa Grande PDA Fee) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. Change in Project Name. |
| 26. JUSTIFICATION |
| These funds are for Staff to review & advertise Consultant PS&E documents. The City has contracted directly with a design consultant to prepare PS&E bid documents. IGA 24-0009573-I has been executed and local funds have been received. Staff - $45K Request for project name to be changed to "South Florence St @ Ash Ave, Casa Grande" to conform with FHWA project naming convention. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in Project Name/Location. Establish a New Project. | Item(s) Approved. |