PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 3/1/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (602) 712-7046 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/6/2022 2:08:01 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
8TH AVE OP EB/WB | BRIDGE REHABILITATION | SX1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 40 | Navajo | 286.0 | F042301D | 1.0 | NHPP |
16. Original Program Budget: $1,010,000 | 17. Original Program Item #: 100198 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$1,010,000 | ($600,000) (0%) | $410,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 600 Item #: 100198 (FY22 8th Ave OP EB/WB - Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ -600 Item #:72322 (.) FY:2022 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Change budget. |
26. JUSTIFICATION |
This project was inadvertently listed in the 2022-2026 Five-Year Program with $600K for Design in FY22. Action was taken on April 27, 2021 to establish the design project in FY21. No additional funds are needed in FY22. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/27/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (602) 712-7046 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/28/2021 1:51:54 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
8TH AVE OP EB/WB | BRIDGE REHABILITATION | SX1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Holbrook | 40 | Navajo | 286.0 | F042301D | 1.0 | NHPP |
16. Original Program Budget: $500,000 | 17. Original Program Item #: 100198 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$500,000 | ($90,000) (0%) | $410,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 500 Item #: 100198 (8th Ave OP EB/WB - Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ -90 Item #:76221 (.) FY:2021 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION (OFF SYSTEM) |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
The existing bridge deck needs rehabilitation using a Polyester Polymer Concrete overlay (mill and replace) and traffic will be managed with phased construction. The project is programmed for construction in FY 24. Staff: $282K Consultant:100K ICAP: $38K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |