PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 3/1/2022 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 6/6/2022 2:08:01 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 8TH AVE OP EB/WB | BRIDGE REHABILITATION | SX1O | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Navajo | 286.0 | F042301D | 1.0 | NHPP |
| 16. Original Program Budget: $1,010,000 | 17. Original Program Item #: 100198 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $1,010,000 | ($600,000) (0%) | $410,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 600 Item #: 100198 (FY22 8th Ave OP EB/WB - Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ -600 Item #:72322 (.) FY:2022 FundSRC:. Desc:CONTINGENCY | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Change budget. |
| 26. JUSTIFICATION |
| This project was inadvertently listed in the 2022-2026 Five-Year Program with $600K for Design in FY22. Action was taken on April 27, 2021 to establish the design project in FY21. No additional funds are needed in FY22. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 4/27/2021 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/28/2021 1:51:54 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 8TH AVE OP EB/WB | BRIDGE REHABILITATION | SX1O | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Holbrook | 40 | Navajo | 286.0 | F042301D | 1.0 | NHPP |
| 16. Original Program Budget: $500,000 | 17. Original Program Item #: 100198 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $500,000 | ($90,000) (0%) | $410,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 500 Item #: 100198 (8th Ave OP EB/WB - Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ -90 Item #:76221 (.) FY:2021 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION (OFF SYSTEM) | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| The existing bridge deck needs rehabilitation using a Polyester Polymer Concrete overlay (mill and replace) and traffic will be managed with phased construction. The project is programmed for construction in FY 24. Staff: $282K Consultant:100K ICAP: $38K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |