PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 4/13/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2021 8:53:54 AM | Olivier Mirza | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
E. KINGMAN TI OP WB BRIDGE | BRIDGE REHABILITATION | ST1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 53.0 | F029501D | 1.0 | NHPP 040-A(231)T |
16. Original Program Budget: $800,000 | 17. Original Program Item #: 100201 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$800,000 | ($46,000) (0%) | $754,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 800 Item #: 100201 (E. Kingman TI OP WB Bridge. Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ -46 Item #:76221 ( ) FY:2021 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION (OFF SYSTEM) |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
The existing bridge deck needs rehabilitation and per the PA the bridge deck will be replaced using phased construction and a crossover to manage the MOT. Staff: $129K Consultant: $557K ICAP: $68K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 11/19/2019 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
11/21/2019 1:04:19 PM | Olivier Mirza | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
E. KINGMAN TI OP WB BRIDGE | BRIDGE REHABILITATION | ST1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 53.0 | F029501L | 1.0 | NHPP 040-A(231)T |
16. Original Program Budget: $100,000 | 17. Original Program Item #: 100201 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$100,000 | $8,000 (0%) | $108,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 100 Item #:100201. (E. Kingman TI OP WB Bridge. Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ 8 Item #:76220 ( ) FY:2020 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new study project. |
26. JUSTIFICATION |
Existing bridge deck is deteriorating. The bridge type, geometry and location of adjacent off ramp and the associated maintenance of traffic is complex. The study project will evaluate alternatives for deck rehabilitation/replacement and approach to construction phasing that will ultimately dictate the design Scope Of Work. Design project programmed for FY21 and construction project programmed for FY22. Staff: $19K Consultant: $79K ICAP:$10K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 11/5/2019 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
11/13/2019 8:29:42 AM | Olivier Mirza | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
E. KINGMAN TI OP WB BRIDGE | BRIDGE REHABILITATION | ST1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 53.0 | F029501L | 1.0 | NHPP |
16. Original Program Budget: $100,000 | 17. Original Program Item #: 100201 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$100,000 | $20,000 (0%) | $120,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 100 Item #:100201. (E. Kingman TI OP WB Bridge. Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ 20 Item #:76220 ( ) FY:2020 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new study project. |
26. JUSTIFICATION |
Existing bridge decks condition requires repairs. The study project will evaluate alternatives for deck rehabilitation/replacement. Design project programmed for FY21 and construction project programmed for FY22. Staff: $32K Consultant: $77K ICAP:$11K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
Arizona Department of Transportation |