PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 3/19/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/22/2024 3:09:08 PM | Arash Ghazanfari | (602) 712-8336 | 205 S 17th Ave, 233, NONE |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WESTERN AVE TI OP SB/NB | BRIDGE REHABILITATION | SS1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 19 | Santa Cruz | 1.17 | F070901D | 1.0 | NHPP |
16. Original Program Budget: $500,000 | 17. Original Program Item #: 100192 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$500,000 | $0 (0%) | $500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 472 Item #: 100192 (Western Ave TI OP SB/NB NHPP) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
This project will remove existing AC, install PPC overlay, maintaining same thickness of existing overlay for both NB and SB of the bridge structure. Full depth deck reconstruction for NB bridge in localized areas (as needed). Consultant: $395K Staff: $57K ICAP: $48K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |