PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 1/25/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/27/2022 10:06:27 AM | Rehnuma Rahman | (602) 712-7382 | 1221 N 21st Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Airport Road TI UP | Bridge Replacement | SR1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | I-17 | Coconino | 337.3 | F036201D | 1 | 017-B(237)T |
16. Original Program Budget: $805,000 | 17. Original Program Item #: 100188 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$805,000 | $875,000 (0%) | $1,680,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 805 Item #: 100188 (Airport Road TI UP - Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ 875 Item #:76222 (.) FY:2022 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
The Design budget of the bridge replacement project was approved at PRB on 5/11/21. The project was advertised to select a design consultant in July, 2021. While preparing the DICE estimate for PRB approval in May, 2021, there were design items missed in the design estimate calculations. Examples of overlooked items are: additional geotechnical investigation due to anticipation of the variable depth to bedrocks, 2 borings at each substructure instead of 1, also seismic lines to map bedrock transversely, Traffic plan and survey aerial mapping to capture the limits along I-17 for MOT crossovers and to capture the limits along the crossroads that could be impacted by the alignment shift, associated field survey to set ground panels, field survey for project features, intersections, roundabouts etc. Also, the team agreed to add a Stage I (15pct) design submittal to evaluate the horizonal alignment alternatives, selecting the span options for selected horizontal alignment, evaluate the MOT concepts. The cost of the Stage I submittal was not included in the design cost estimate. The ADOT team evaluated the cost proposal submitted by the design consultant and provided comments to reduce costs in a few items. The team agreed that the final cost proposal provided by the consultant was appropriate. Staff: $5K Consultant: $794K ICAP: $86K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 12/21/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/21/2021 9:27:31 AM | Rehnuma Rahman | (602) 712-7382 | 1221 N 21st Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Airport Road TI UP | Bridge Replacement | SR1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | I-17 | Coconino | 337.3 | F036201D | 1 | 017-B(237)T |
16. Original Program Budget: $805,000 | 17. Original Program Item #: 100188 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$805,000 | $875,000 (0%) | $1,680,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 805 Item #:10018 (.) FY:0 FundSRC: Desc: | $ 875 Item #:76222 (.) FY:2022 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
Based on the recommendation from the bridge group, a decision was made for complete replacement of the bridge. The scoping memo will address the type of bridge to be selected which was not originally accounted for. Supplemental survey will be performed by the consultant to provide additional shots for the existing bridges, edges of the pavement, right of way monuments, section corners etc. A subconsultant will be hired to perform the base mapping for the project. Additionally geotechnical work performed by a sub consultant will include borings on the bridge, coring for the new pavement design and the proposed I-17 median for temporary crossover, geophysical study to identify voids or layers/pockets weak rock in limestone at each abutment. Staff: -$5K Consultant: $794K ICAP: $86K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Request Withdrawn. |
PRB Meeting Date: 5/11/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/14/2021 9:51:57 AM | Rehnuma Rahman | (602) 712-7382 | 1221 N 21st Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Airport Road TI UP | Bridge Replacement | SR1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | I-17 | Coconino | 337.3 | F036201D | 1 | 017-B(237)T |
16. Original Program Budget: $800,000 | 17. Original Program Item #: 100188 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$800,000 | $5,000 (0%) | $805,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 800 Item #:10018 (.) FY:0 FundSRC: Desc: | $ 5 Item #:76221 (.) FY:2021 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION (OFF SYSTEM) |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
Complete replacement is recommended, based on the bridge inspection report dated July, 2020. These funds will be used to secure a consultant to conduct the final design of the project. ADOT will perform the surveying and any pavement design related work. Staff: $182K Consultant: $550K ICAP: $73K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 4/20/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2021 10:10:07 AM | Rehnuma Rahman | (602) 712-7382 | 1221 N 21st Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
AIRPORT ROAD TI UP | BRIDGE REPLACEMENT | SR1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | I-17 | Coconino | 337.3 | F036201C | 1 | 017-B(237)T |
16. Original Program Budget: $4,000,000 | 17. Original Program Item #: 100188 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$4,000,000 | $5,500,000 (0%) | $9,500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 4000 Item #:10018 ( ) FY:0 FundSRC: Desc: | $ 5500 Item #:76223 (.) FY:2023 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 23 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
This project is replacing the 208ft X 33ft bridge with an approximately 228ft X 44ft new bridge. The estimate includes cost for the roadway and ramp improvements necessary to facilitate the bridge replacement. The cost estimation includes the 30pct for unidentified items and 6pct for two years of cost inflation. ICAP is included in this request. Contingent on approval by PPAC, this will be included in the FY22-FY26 Five Year Program. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/20/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/21/2021 8:46:26 AM | Rehnuma Rahman | (602) 712-7382 | 1221 N 21st Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Airport Road TI UP | Bridge Replacment | SR1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | I-17 | Coconino | 337.3 | F036201D | 1 | 017-B(237)T |
16. Original Program Budget: $800,000 | 17. Original Program Item #: |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$800,000 | $86,000 (0%) | $886,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 800 Item #:10018 (.) FY:0 FundSRC: Desc: | $ 86 Item #:76221 (.) FY:2021 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION (OFF SYSTEM) |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
The bridge is recommended to be replaced entirely based on the bridge inspection report dated July, 2020. These funds will be used to secure a consultant to conduct scoping and final design of the project. ADOT will perform the surveying and any pavement design related work. Staff: $211K Consultant: $595K ICAP: $80K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. Return with revised estimate. |
Arizona Department of Transportation |