PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 8/18/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/8/2026 8:53:43 AM Skye Gentile Bush (602) 568-6782 205 S 17th Ave, Phoenix, AZ 85007
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Payson Wildfire Evacuation Route New Roadway sp1q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff Gila T072201L 0.74 PAY-0(209)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104628
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $319,000 (0%) $319,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 25-0011438-I
$ 300 Item #:90000 (Fed Earmark) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 27 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Scoping Project.
26. JUSTIFICATION
Evaluate the construction of 3,900 linear feet of asphalt paved roadway within a 200 foot wide easement crossing the Tonto National Forest. Contingent upon receipt of Town of Payson funding. ADOT review: $12k Consultant: $307k Total: $319k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation