PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 4/16/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/19/2024 9:00:46 AM | Rashidul Haque | (602) 712-7352 | 205 S 17th Ave, 295, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
EAST WILLCOX TI UP | BRIDGE DECK REHABILITATION | SJ1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 10 | Cochise | 344.5 | F029101C | 0.1 | NHPP 010-F(229)T |
16. Original Program Budget: $2,000,000 | 17. Original Program Item #: 100184 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$2,000,000 | $0 (0%) | $2,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 2000 Item #: 100184 ( ) FY:0 FundSRC: Desc: | $ 2000 Item #: 76224 ( ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | 24 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Advance project to FY24 |
26. JUSTIFICATION |
The project is ready to advertise. Capacity exists to deliver this project in FY24. This request is to advance construction from FY25 to FY24 to advertise this project in FY24. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 10/15/2019 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/24/2020 7:57:25 AM | Rashidul Haque | (602) 712-7352 | 205 S 17th Ave, 295, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
EAST WILLCOX TI UP | BRIDGE DECK REHABILITATION | SJ1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 10 | Cochise | 344.0 | F029101D | 1.0 | NHPP |
16. Original Program Budget: $500,000 | 17. Original Program Item #: 100184 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$500,000 | $118,000 (0%) | $618,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 500 Item #:100184. (East Willcox TI UP Bridge Rehabilitation) FY:0 FundSRC: Desc: | $ 118 Item #:76220 ( ) FY:2020 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish project |
26. JUSTIFICATION |
East Willcox TI (UP) needs bridge deck rehabilitation. Consultant: $467K Staff: $95K ICAP: $56K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |