PRB Meeting Date: 6/18/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/21/2024 9:38:14 AM Stephanie Brown (602) 712-4424 206 S 17th Ave, 157, 139A
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
10: Knox Rd Pedestrian Bridge CONSTRUCT PEDESTRIAN BRIDGE SI1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 159.27 _ 0.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $12,930,000 17. Original Program Item #: 102456
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$12,930,000 ($12,930,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10308 Item #:49824 (94.34pct Federal Aid) FY:0 FundSRC: Desc: $ -10308 Item #:49824 (94.34pct Federal Aid) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 2024 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Decrease budget Change Fiscal Year
26. JUSTIFICATION
To be programmed by MAG in a future Fiscal Year.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
CHANGE IN FY Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 6/18/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/21/2024 8:37:03 AM Stephanie Brown (602) 712-4424 206 S 17th Ave, 157, 139A
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
10: Knox Rd Pedestrian Bridge CONSTRUCT PEDESTRIAN BRIDGE SI1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 159.27 _ 0.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102456
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $1,235,000 (0%) $1,235,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 1235 Item #:102456 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project
26. JUSTIFICATION
Establish Design in FY25. MAG established this Design this project in FY25 at a prior meeting.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/12/2024 11:58:02 AM Stephanie Brown (602) 712-4424 206 S 17th Ave, 157, 139A
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
10: Knox Rd Pedestrian Bridge CONSTRUCT PEDESTRIAN BRIDGE SI1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix I-10 Maricopa 159.27 _ 0.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102456
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $1,314,000 (0%) $1,314,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 1314 Item #:49925 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project
26. JUSTIFICATION
This project was in the MAG TIP in FY23 and was never established or funded. Move Design to FY25 pending action by MAG. Additional coordination with Phoenix and Tempe needs to occur before design can commence.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/12/2024 11:02:15 AM Stephanie Brown (602) 712-4424 206 S 17th Ave, 157, 139A
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
10: Knox Rd Pedestrian Bridge CONSTRUCT PEDESTRIAN BRIDGE SI1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix I-10 Maricopa 159.27 _ 0.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $12,930,000 17. Original Program Item #: 102456
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$12,930,000 $0 (0%) $12,930,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2004 Item #:102456 (100pct RARF ) FY:0 FundSRC: Desc: $ -10308 Item #:49824 (94.34pct Federal Aid) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 2024 21a. Fiscal Year: 2026  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Move construction to FY26 pending MAG action.
26. JUSTIFICATION
Additional coordination with Phoenix and Tempe needs to occur before construction can commence.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Request Withdrawn.