PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 8/8/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
8/10/2023 8:50:27 AM Thomas Oreilly (602) 712-2587 1611 W Jackson St, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
E. OF VICKSBURG - JCT SR 72 PAVEMENT REHABILITATION SF1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 60 La Paz 45.0 F050301C 3.6 STBG060-A(216)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $6,800,000 17. Original Program Item #: 102473
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$6,800,000 $1,860,000 (0%) $8,660,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 6800 Item #:102473 ( ) FY:0 FundSRC: Desc: $ 1860 Item #:72524 ( ) FY:2024 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 24 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 12/8/2023 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget and change project name.
26. JUSTIFICATION
The limits of the project were increased from 3.6 miles to 3.88 miles to include fog coat through the Vicksburg roundabout and eliminate a gap in recent pavement rehabilitation projects. The name for the project is now "Vicksburg - SR72". Additional funding is needed due to increases in unit cost for AC items, striping, and concrete. This request includes ICAP.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/19/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/22/2022 8:54:04 AM Jeffrey Davidson (602) 712-8534 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
E. OF VICKSBURG - JCT SR 72 PAVEMENT REHABILITATION SF1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 60 La Paz 46.0 F050301D 3.6  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $265,000 17. Original Program Item #: 102473
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$265,000 $56,000 (0%) $321,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 265 Item #:102473 (.) FY:0 FundSRC: Desc: $ 56 Item #: 72522 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new Design Project
26. JUSTIFICATION
The pavement on US 60 from E of Vicksburg to the Junction of SR 72 is in need of rehabilitation. This project is to rehabilitate the existing pavement Staff $235K Consultant $55K ICAP $31K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation