PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 3/12/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/14/2024 9:23:39 AM Sandy Thoms , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
HAPPY VALLEY RD - SR 74 PAVEMENT REHABILITATION SD1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 17 Maricopa 218.4 F049501D 5.7 NHPP017-A(261)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $418,000 17. Original Program Item #: 102469
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$418,000 $10,000 (0%) $428,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 395 Item #:102469 (NHPP) FY:0 FundSRC: Desc: $ 10 Item #:72524 ( PRESERVATION) FY:2024 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
This request is to increase the design budget. After construction advertisement, requests arose from Central District for various design changes. This required design re-work and issuance of multiple addendums, resulting in staff charges in excess of what was anticipated. Staff: $9K ICAP: $1K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 11/21/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/22/2023 3:05:07 PM Sandy Thoms , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
HAPPY VALLEY RD - SR 74 PAVEMENT REHABILITATION SD1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 17 Maricopa 218.4 F049501D 5.7 NHPP017-A(261)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $395,000 17. Original Program Item #: 102469
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$395,000 $23,000 (0%) $418,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 395 Item #:102469 (NHPP) FY:0 FundSRC: Desc: $ 23 Item #:72524 ( ) FY:2024 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
This request is to increase the design budget. During project development, the pavement treatment type was changed and required some reworking of the plans. There were also last-minute changes to striping impacting the plans. Additionally, the environmental clearance took more effort than anticipated requiring additional cultural coordination as well as flagging. Staff: $20K ICAP: $3K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 9/26/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/15/2023 12:09:53 PM Sandy Thoms , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
HAPPY VALLEY RD - SR 74 PAVEMENT REHABILITATION SD1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 17 Maricopa 218.2 F049501D 6.2 NHPP017-A(261)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $395,000 17. Original Program Item #: 102469
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$395,000 $0 (0%) $395,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 395 Item #:102469 (NHPP) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change project limits.
26. JUSTIFICATION
This request is to update the starting and ending milepost limits for this pavement rehab project after coordination with adjacent projects. The starting milepost would change to 218.44 which would coincide with where improvements ended on the recent Happy Valley Rd TI reconstruction. The ending milepost would change to 224.16 which would coincide with a separate pavement rehab project to the north that is currently in design (F0554). These changes reduce the overall project length to 5.72 miles.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
CHANGE PROJECT LIMITS Item(s) Approved.


PRB Meeting Date: 4/5/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/7/2022 9:29:54 AM Sandy Thoms , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
HAPPY VALLEY RD - SR 74 PAVEMENT REHABILITATION SD1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 17 Maricopa 218.2 F049501D 6.2  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $247,000 17. Original Program Item #: 102469
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$247,000 $148,000 (0%) $395,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 247 Item #:102469 (NHPP) FY:0 FundSRC: Desc: $ 148 Item #:72522 ( ) FY:2022 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish design project.
26. JUSTIFICATION
This request is to establish a design project for pavement rehabilitation on I-17 from Happy Valley Rd to SR 74. Staff = $302k Consultant = $55k ICAP = $38k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox