6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MIDGLEY/WILSON CANYON BRIDGE | REHABILITATE BRIDGE | SC1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 89A | Coconino | 376.0 | F079201D | 0.1 | A89-B(227)T |
16. Original Program Budget: $500,000 | 17. Original Program Item #: 104381 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$500,000 | $0 (0%) | $500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 500 Item #:104381 (100pct State Funds) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
Midgley Bridge over Wilson Canyon is in fair condition and requires rehabilitation activities to extend the life of the structure. Rehabilitation to include cleaning/painting of superstructure, approach slab rehabilitation and bridge joint replacement. Consultant $172K Staff $288K ICAP $40K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |