PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 3/3/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/5/2026 10:27:50 AM | Chris Moore | (757) 469-6679 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| TOPOCK PORT OF ENTRY | CONSTRUCT INSPECTION PIT | SB1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 40 | Mohave | 3.6 | F081701D | 0.0 | 040-A(386)T |
| 16. Original Program Budget: $740,000 | 17. Original Program Item #: 104398 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $740,000 | $100,000 (0%) | $840,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 425 Item #:104398 (STBGP $424,530) FY:0 FundSRC: Desc: | $ 100 Item #:72326 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. |
| 26. JUSTIFICATION |
| This project will construct an inspection pit at the Topock Port of Entry. Request budget increase for additional design efforts for physical security and IT associated with the CCTV system. Consultant $737k Staff $55k ICAP $48k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 11/25/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 2/11/2026 11:10:46 AM | Chris Moore | (757) 469-6679 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| TOPOCK PORT OF ENTRY | CONSTRUCT INSPECTION PIT | SB1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 40 | Mohave | 3.6 | F081701D | 0.0 | 040-A(386)T |
| 16. Original Program Budget: $450,000 | 17. Original Program Item #: 104398 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $450,000 | $290,000 (0%) | $740,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 425 Item #:104398 (STBGP $424,530) FY:0 FundSRC: Desc: | $ 290 Item #:72326 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. |
| 26. JUSTIFICATION |
| This project will construct an inspection pit at the Topock Port of Entry. Request budget increase for additional design efforts for physical security and IT associated with the CCTV system. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 10/7/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/9/2025 8:51:21 AM | Chris Moore | (757) 469-6679 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| TOPOCK PORT OF ENTRY | CONSTRUCT INSPECTION PIT | SB1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 40 | Mohave | 3.6 | F081701C | 0.0 | 040-A(386)T |
| 16. Original Program Budget: $6,979,000 | 17. Original Program Item #: 104398 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $6,979,000 | $0 (0%) | $6,979,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 6584 Item #:104398 (STBGP $6,584,140) FY:0 FundSRC: Desc: | $ -6979 Item #:74327 (.) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | FY27 | 21a. Fiscal Year: | FY29 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Defer project |
| 26. JUSTIFICATION |
| This project will construct an inspection pit at the Topock Port of Entry. Request to move the advertisement to FY29 Q1 based on ECD priorities. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. | Request Withdrawn. |
| PRB Meeting Date: 3/25/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/27/2025 12:07:37 PM | Chris Moore | (757) 469-6679 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| TOPOCK PORT OF ENTRY | CONSTRUCT INSPECTION PIT | SB1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 40 | Mohave | 3.6 | F081701D | 0.0 | 040-A(386)T |
| 16. Original Program Budget: $450,000 | 17. Original Program Item #: 104398 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $450,000 | $0 (0%) | $450,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 425 Item #:104398 (STBGP $424,530) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project |
| 26. JUSTIFICATION |
| This project will construct an inspection pit at the Topock Port of Entry. Staff $53k Consultant $364k ICAP $33k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |