PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 7/7/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/9/2026 2:17:35 PM Arash Ghazanfari (602) 712-8336 205 S 17TH AVE, 233, NONE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIORDAN BNSF RAILROAD OP EB/WB REPLACE BRIDGE RX1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190.0 F077201D 1.0 040-C(230)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,500,000 17. Original Program Item #: 104376
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,500,000 $36,000 (0%) $2,536,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2359 Item #:104376 ( ($2,358,500)) FY:0 FundSRC: Desc: $ 36 Item #:72727 (State 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget.
26. JUSTIFICATION
The rock cut west of I-40 Riordan Bridge produces rockfall that periodically lands to the WB I-40 A-1 Mountain Road off-ramp or on the WB I-40 lanes. To prevent that, rockfall mitigation is proposed that consists of draped mesh anchored to the slope. Consultant: $32K Staff: $2K ICAP: $2K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 6/23/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/26/2026 1:29:49 PM Arash Ghazanfari (602) 712-8336 205 S 17TH AVE, 233, NONE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIORDAN BNSF RAILROAD OP EB/WB REPLACE BRIDGE RX1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190.0 F077201C 1.0 040-C(230)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $53,000,000 17. Original Program Item #: 104376
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$53,000,000 $0 (0%) $53,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2080 Item #:104376 ((State match $2,080,051.00) -FY28) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: FY27 21a. Fiscal Year: FY27  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 9/10/2026 23a. Bid Adv Date: 11/30/2026

25. DESCRIPTION OF REQUEST
Change Schedule.
26. JUSTIFICATION
This request is to change the bid advertisement schedule from FY27/Q1 to FY27/Q2 to enable a combined advertisement of this project with pavement rehab project F0843. This project is within the limits of pavement rehab project F0843.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 10/22/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/25/2024 9:32:37 AM Arash Ghazanfari (602) 712-8336 205 S 17TH AVE, 233, NONE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIORDAN ATSF RAILROAD OVERPASS EB #332/WB #897 REPLACE BRIDGE RX1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 190.0 F077201D 1.0 040-C(230)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,500,000 17. Original Program Item #: 104376
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,500,000 $0 (0%) $2,500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2359 Item #:104376 ( ($2,358,500)) FY:0 FundSRC: Desc: $ -2500 Item #:76225 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project is to replace two bridges along I-40 EB/WB from MP190 to MP191. Project name to be changed to: "RIORDAN BNSF RAILROAD OP EB/WB" Consultant: $2,121K Staff: $196K ICAP: $183K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox