PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 10/22/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/25/2024 9:32:37 AM | Arash Ghazanfari | (602) 712-8336 | 205 S 17TH AVE, 233, NONE |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
RIORDAN ATSF RAILROAD OVERPASS EB #332/WB #897 | REPLACE BRIDGE | RX1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Flagstaff | 40 | Coconino | 190.0 | F077201D | 1.0 | 040-C(230)T |
16. Original Program Budget: $2,500,000 | 17. Original Program Item #: 104376 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$2,500,000 | $0 (0%) | $2,500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 2359 Item #:104376 ( ($2,358,500)) FY:0 FundSRC: Desc: | $ -2500 Item #:76225 (.) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This project is to replace two bridges along I-40 EB/WB from MP190 to MP191. Project name to be changed to: "RIORDAN BNSF RAILROAD OP EB/WB" Consultant: $2,121K Staff: $196K ICAP: $183K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |