PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 11/26/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/2/2024 8:59:02 AM | Wesley Scatena | (602) 712-8555 | 205 S 17th Ave, , E741 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
UPPER ELGIN RD @ BABOCOMARI CREEK | REPLACE BRIDGE | QP1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Santa Cruz | SSC | T059901D | 0.0 | OSB SSC-0(211)T |
16. Original Program Budget: $54,000 | 17. Original Program Item #: 104507 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$54,000 | $0 (0%) | $54,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0009764-I |
$ 54 Item #:104507 (100pct OSB) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This project will replace an existing single-lane, steel truss bridge on Upper Elgin Road across Babocomari Creek (structure no. 8165) to increase the load rating and allow for two-way traffic. Staff: $54K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 11/26/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/2/2024 8:59:57 AM | Wesley Scatena | (602) 712-8555 | 205 S 17th Ave, , E741 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
UPPER ELGIN RD @ BABOCOMARI CREEK | REPLACE BRIDGE | QP1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Santa Cruz | SSC | T059903D | 0.0 | OSB SSC-0(211)T |
16. Original Program Budget: $541,000 | 17. Original Program Item #: 104507 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$541,000 | $0 (0%) | $541,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0009764-I |
$ 541 Item #:104507 (100pct OSB) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This project will replace an existing single-lane, steel truss bridge on Upper Elgin Road across Babocomari Creek (structure no. 8165) to increase the load rating and allow for two-way traffic. Consultant: $541K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |