PRB Meeting Date: 4/15/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/18/2025 10:10:17 AM | Alyssa Young | (480) 932-9468 | 205 S 17TH AVE, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CROOKTON RD @ BNSF RR OP | REHABILITATE BRIDGE | QK1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Yavapai | YYV | T059201C | 0.0 | OSB YYV-0(225)T |
16. Original Program Budget: $2,890,000 | 17. Original Program Item #: 104505 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$2,890,000 | $0 (0%) | $2,890,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0009721 |
$ 645 Item #:OTHR25 (Local Contribution ($644,312)) FY:0 FundSRC: Desc: | $ -645 Item #:OTHR25 (Local Contribution ($644,312)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | 26 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 5/30/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer project |
26. JUSTIFICATION |
Defer project from FY25 to FY26. Project encountered additional environmental commitments and reports due to the abandoned bridge requiring demolition. The bridge is historic, therefore triggering additional evaluation, reports and reviews. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Schedule. | Item(s) Approved. |
PRB Meeting Date: 2/25/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/8/2025 1:35:52 PM | Alyssa Young | (480) 932-9468 | 205 S 17TH AVE, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CROOKTON RD @ BNSF RR OP | REHABILITATE BRIDGE | QK1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Yavapai | YYV | T059201C | 0.0 | OSB YYV-0(225)T |
16. Original Program Budget: $2,890,000 | 17. Original Program Item #: 104505 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$2,890,000 | $0 (0%) | $2,890,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 2245 Item #:76425 ( ) FY:0 FundSRC: Desc: | $ -2245 Item #:76425 (.) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | 27 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 5/30/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer project |
26. JUSTIFICATION |
Defer project from FY25 to FY27 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Schedule. | Request Withdrawn. |
PRB Meeting Date: 8/13/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/8/2025 1:38:50 PM | Alyssa Young | (480) 932-9468 | 205 S 17TH AVE, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CROOKTON RD @ BNSF RR OP | REHABILITATE BRIDGE | QK1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Yavapai | YYV | T059201D | 0.0 | OSB YYV-0(225)T |
16. Original Program Budget: $45,000 | 17. Original Program Item #: 104505 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$45,000 | $0 (0%) | $45,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0009721 |
$ 45 Item #:104505 (100 pct OSB $45,000) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The project is to rehabilitate the railroad bridge by replacing existing deck, repair bridge approaches and update the rail system to current guidelines. Staff: $45K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |