| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 11/6/2025 10:19:03 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CHOLLA CANYON RANCH ROAD - EAST OLDEUP HILLSIDE | PAVEMENT REHABILITATION | PW1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 93 | Mohave | 128 | F076001C | 3 | 093-B(227)T |
| 16. Original Program Budget: $14,548,000 | 17. Original Program Item #: 104405 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $14,548,000 | $3,000,000 (0%) | $17,548,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 14548 Item #:104405 ( ) FY:0 FundSRC: Desc: | $ 3000 Item #:72326 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase Budget. Change Beginning Milepost. |
| 26. JUSTIFICATION |
| The subgrade on SB US93 between approximate MP 129.4 and MP 129.7 has been identified as being unstable. During the design of the project, following the engineering investigations, the design team recommended reconstructing the roadway within the area of unstable subgrade using High Survivability Separation Geotextile Fabric, Geogrid Base Reinforcement, Aggregate Base, thicker asphaltic pavement, and drainage improvements. The request also includes a change of beginning milepost from MP 128.0 to MP 127.67, to avoid a gap in pavement treatment between this and a recently completed pavement rehabilitation project. The additional construction cost to rehab the pavement in this gap, is included in this request. ICAP is included in the request. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 4/23/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/25/2024 10:38:32 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CHOLLA CANYON RANCH ROAD - EAST OLDEUP HILLSIDE | PAVEMENT REHABILITATION | PW1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 93 | Mohave | 128 | F076001D | 3 | 093-B(227)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104405 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $490,000 (0%) | $490,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 490 Item #:72524 (100pct State) FY:2024 FundSRC:. Desc:PRESERVATION | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new design project |
| 26. JUSTIFICATION |
| This project is a pavement rehabilitation on US 93. Construction is scheduled in FY27 in the FY25 - FY29 Tentative Program. Staff - $130k Consultant - $312k ICAP - $48k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |