PRB Meeting Date: 4/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/25/2024 12:08:37 PM Alyssa Young (480) 932-9468 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
CA BORDER - DOME ROCK RD PAVEMENT REHABILITATION PT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 10 La Paz 0.0 F076201D 11.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104413
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $690,000 (0%) $690,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 690 Item #:72524 (100 pct state funds) FY:2024 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
The project will design and implement pavement rehabilitation to Interstate 10 starting at milepost 0 (CA Border) and ending at milepost 11 (Dome Rock Rd) Construction is scheduled for FY28. Consultant- $60k Staff- $563k ICAP- $67k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox