PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/8/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/10/2025 10:53:36 AM Rashidul Haque (602) 712-7352 205 S 17TH AVE, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VERRADO WAY - 99TH AVE CONVERT HPS TO LED LIGHTING PS1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 120.0 F074501C 13.0 010-B(224)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $540,000 17. Original Program Item #: 104497
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$540,000 $2,460,000 (0%) $3,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 509 Item #:104497 (Federal (94.3pct) CRP) FY:0 FundSRC: Desc: $ 2320 Item #:72325 (Federal (94.3 pct--$2,318,780)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/6/2025 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase in budget
26. JUSTIFICATION
This project is to convert HPS lighting to LED. The programmed amount is incorrect. The initial estimate was based on a high level overview without field verifications or a detail breakdown. The majority of the fixtures required for the project are high mast, high-powered luminaires. The current estimate takes into account this type of lighting and its higher unit prices. Traffic Control and Construction Engineering were underestimated. In addition, the repair of existing conductors and modifying high mast lowering rings were added to the scope of work. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 3/25/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/27/2025 12:39:36 PM Jeffrey Davidson (602) 712-8534 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VERRADO WAY - 99TH AVE CONVERT HPS TO LED LIGHTING PS1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 120 F074501C 13  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $540,000 17. Original Program Item #: 104497
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$540,000 $1,952,000 (0%) $2,492,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 509 Item #:104497 (Federal (94.3pct) CRP) FY:0 FundSRC: Desc: $ 1841 Item #:70925 (State (94.3pct)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 5/30/2025 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase in budget
26. JUSTIFICATION
This project is to convert from HPS Lighting to LED Lighting. The initial scoping estimate was higher than what was inadvertently programmed for the budget. Since the initial estimate, unit prices for the LED lighting fixtures have increased. This requested budget increase will account for these two items. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Request Withdrawn.


PRB Meeting Date: 4/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/25/2024 11:12:02 AM Jeffrey Davidson (602) 712-8534 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VERRADO WAY - 99TH AVE CONVERT HPS TO LED LIGHTING PS1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 120.0 F074501D 13.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: .
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $260,000 (0%) $260,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 260 Item #:70924 (Carbon Reduction Program ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project will convert from HPS Lighting to LED Lighting as part of the Carbon Reduction Program. Construction is anticipated in FY25. Staff $64K Consultant $170K ICAP $26K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation