PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 10/22/2019
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/24/2019 11:33:35 AM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
BABBITTS TANK WB & BUFFALO RANGE TI OP EB/WB CONSTRUCT BRIDGE REHABILITATION PF1N
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 224.7 H892801C 1.0 NHPP040-D(235)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,600,000 17. Original Program Item #: 8372
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,600,000 $650,000 (0%) $3,250,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2600 Item #:8372 ( ) FY:2020 FundSRC:. Desc:Babbits Tank WB & Buffalo Range TI OP EB/WB $ 650 Item #:76220 ( ) FY:2020 FundSRC:. Desc:BRIDGE REPLACEMENT & REHABILITATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 20 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 11/8/2019 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 12/6/2019 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget.
26. JUSTIFICATION
The following work was not included at Stage 3: Existing Detour Removal ($40k) The following work was underestimated at Stage 3: Paving, Subbase, Traffic Control, Mobilization, Guardrail, Erosion Control, Contractor Quality Control ($225k) The following work was underestimated at Stage 3 and had quantity increases: Bridges ($300k) Incremental increases for Contingency and ICAP ($85k)
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 2/12/2019
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/25/2019 2:12:27 PM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
BABBITTS TANK BR WB & BUFFALO RANGE TI OP EB CONSTRUCT BRIDGE REHABILITATION PF1N
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 224.7 H892801R 1.0 NHPP040-D(235)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 8372
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $3,000 (0%) $3,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 3 Item #:76219 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish ROW Sub-phase.
26. JUSTIFICATION
TCE is required to replace the bridge superstructure. Cost of acquiring TCE is $2500. TCE 2.5K ICAP .25K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 1/24/2017
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/27/2017 12:39:25 PM Gary Sun (602) 712-4711 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
BABBITTS TANK BR WB #1385 & BUFFALO RANGE TI OP #1 DESIGN BRIDGE DECK REHABILITATION PF1N
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 224.7 H892801D 1.0 040-D(235)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $750,000 17. Original Program Item #: 8372
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$750,000 ($250,000) (0%) $500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 750 Item #:8372 ( ) FY:2020 FundSRC:. Desc:Babbits Tank WB & Buffalo Range TI OP EB/WB $ -250 Item #:72317 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Project.
26. JUSTIFICATION
Scoping is complete, and it consists of a deck replacement for Babbitts Tank Wash WB Bridge and a deck rehabilitation for Buffalo Range TI OP. Final Design is ready to be performed. Based on the recommended alternatives the programmed amount is in excess of the final design needs. This is a FY20 construction project. Staff $430K Consultant $32K ICAP $38K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 5/12/2015
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/25/2015 2:18:51 PM David Benton (602) 712-7910 205 S 17th Ave, , 631E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Babbitts Tank Br WB #1385 & Buffalo Ranch TI OP #1386/1387 Scoping-Deck Rehabilitation PF1N
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 40 Coconino 224.7 H892801D 2.0 040-D(235)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $155,000 (0%) $155,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 155 Item #:72315 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish scoping project.
26. JUSTIFICATION
Bridge decks are deteriorating and require an assessment of rehabilitation alternatives to establish construction project. Funding Request: Consultant = 120k Staff = 20K ICAP = 15K Total = 155K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval. Special PPAC Meeting on May 19th, at 3:00pm.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation