PRB Meeting Date: 1/28/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/31/2025 9:18:47 AM Connie Corvalan (602) 712-2278 205 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VAL VISTA - SOUTHERN CONVERT HPS TO LED LIGHTING PE1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 202L Maricopa 19.0 F074801C 11.0 202-B(207)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $800,000 17. Original Program Item #: 104501
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$800,000 $600,000 (0%) $1,400,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 754 Item #:104501 (CRP Flex ($754,400)) FY:0 FundSRC: Desc: $ 600 Item #:70925 (Carbon Reduction Program) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget Change project limits
26. JUSTIFICATION
This project is to convert HPS lighting to LED. The original programmed amount was based on initial estimates that did not take into account the type of lighting fixtures required and their varied unit costs. This request is to also change the beginning MP from 19.0 to 18.0, and increase the project length to 12 miles. This segment was missed in the original scoping and if not included would leave a gap of HPS lighting. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
CHANGE PROJECT LIMITS Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 1/14/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/14/2025 9:49:40 AM Connie Corvalan (602) 712-2278 205 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VAL VISTA - SOUTHERN CONVERT HPS TO LED LIGHTING PE1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 202L Maricopa 19.0 F074801C 11.0 202-B(207)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $800,000 17. Original Program Item #: .
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$800,000 $0 (0%) $800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 800 Item #:70925 (Carbon Reduction Program) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change project limits.
26. JUSTIFICATION
This request is to change the beginning MP from 19.0 to 18.0, and increase the project length to 12 miles. This segment was missed in the original scoping. This change will not require additional funds.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
CHANGE PROJECT LIMITS Request Withdrawn.


PRB Meeting Date: 4/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/25/2024 11:24:13 AM Connie Corvalan (602) 712-2278 205 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VAL VISTA - SOUTHERN CONVERT HPS TO LED LIGHTING PE1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 202L Maricopa 19.0 F074801D 11.0 202-B(207)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: .
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $260,000 (0%) $260,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 260 Item #:70924 (Carbon Reduction Program ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This consultant-designed project will convert High Pressure Sodium (HPS) lighting to Light-emitting diode (LED) lighting as part of the Carbon Reduction Program. Construction is anticipated in FY25. Staff: $65k Consultant: $170k ICAP: $25k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation