PRB Meeting Date: 3/19/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/22/2024 3:45:57 PM Raymundo Baca (602) 679-0072 7130 W Fairview St, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SMF Capital Maintenance (FY24) STRIPING OU1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 202 Maricopa 55 F060401C 22  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,830,000 17. Original Program Item #: 101911
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,830,000 $0 (0%) $3,830,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2893 Item #:101911 (CAPITAL MAINTENANCE STRIPING ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 24 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project
26. JUSTIFICATION
Striping work for FY24 on South Mountain Freeway. ICAP is include in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.